Thanakorn de6ff85fa1 docs(sdlc): address 23/09 review feedback
Trace every CR to a test case or delivered document, drop the draft FR/NFR remark column, record lessons learned, replace the three change reports with a change-control register, add high-level diagrams and wireframes to the design, plan verification rounds with dates and hours, and base the validation result on the Customer Requirements.
2026-09-24 08:45:20 +07:00

33 lines
1.5 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# SDLC work-product seed
Regenerates every ISO/IEC 29110 work product under `sdlc/` from controlled project
data, in the layout of the audited `200-TAS-25-001-00` reference package: Thai
section headings, a `Document No` control block, and Secretary / Reviewer /
Approval signature tables on every document.
`sdlc/` is generated output. Edit the data files here, never the Markdown.
## Files
| File | Contents |
|---|---|
| `project.mjs` | People, dates, project code, scope, deliverables, Customer Requirements (CR01–CR14) |
| `engineering.mjs` | Software Requirements (SR01–SR09), Software Units, Test Cases, and the CR→SR→Unit→Test mapping |
| `history.mjs` | Work Schedule, reporting periods, meetings, Correction Register, Change Reports |
| `lib.mjs` | Buddhist-calendar dates, Markdown tables, signature blocks |
| `format.mjs` | The shared work-product scaffold |
| `figures.mjs` | Software Design diagrams and wireframes, drawn as SVG; `scripts/sdlc-delivery/render-figures.mjs` rasterises them into `figures/*.png` |
| `docs-*.mjs` | One generator per work product |
| `build.mjs` | Writes all documents and checks no folder is left empty |
## Usage
```bash
node scripts/sdlc-seed/build.mjs # regenerate sdlc/ only
bash scripts/build-sdlc-delivery.sh # seed, render to PDF, then verify
```
The traceability chain is validated at import time: every Customer Requirement
must resolve to existing Software Requirements, Software Units, and a Test Case,
or the build fails.