Verification Results

Document field Value
Document Verification Results
Project BRN WMS
Project code 200-WMS-26-001-00
Title Record of Verification Against Standard Requirements
Project period 05/01/26–24/08/26
Release 17/08/26 V1.0
Standard ISO/IEC 29110 Basic Profile
Review round Round 2 completed 17/08/26 — Round 2A document-control verification and Round 2B technical work-product verification
Organizer Apirach Supattaratpateep (Project Manager), Noppong Chareunsook (System Analyst), Thanakorn Sathitwitayakul (Developer)
Round 2A verifier Yaowalak Bangchomphoo — Document Control, independent of the document preparer
Round 2B technical reviewers Noppong Chareunsook — System Analyst; Parin Ngamkham — QA / Tester; Apirach Supattaratpateep — Project Manager
Status Final — Round 2 document-control and technical verification complete

Objective

Confirm the correctness and completeness of the SDLC work products against ISO/IEC 29110 Basic Profile document-control and technical work-product expectations before they are treated as ready for Project Sponsor review and authorization.

1. Deliverables under review

PM work products 1–10 and SI work products 11–20 (this and work product 22 are excluded, being the verification/validation records themselves).

2. Round 2A — Document-control verification

Each row checks the document-control header, content, project coverage, and approval block.

ID Work product Header complete Purpose met Evidence basis disclosed Approval block present Result
VR-01 Statement of Work Yes Yes N/A Yes Passed
VR-02 Project Plan (Work Schedule, SPP, Customer Requirements) Yes Yes Yes, where applicable Yes Passed
VR-03 Progress Status Records (13) Yes Yes Yes Yes Passed
VR-04 Correction Register Yes Yes Yes Yes Passed
VR-05 Acceptance Report Yes Yes Yes Yes Passed
VR-06 Change Report (CH-001–CH-003) Yes Yes Yes Yes Passed
VR-07 Meeting Record (MTG-001–MTG-004) Yes Yes Yes — each record discloses its evidence basis and marks unrecorded fields Yes Passed
VR-08 Software Configuration Yes Yes Yes Yes Passed
VR-09 Project Repository Yes Yes Yes Yes Passed
VR-10 Project Repository (Backup) Yes Yes Yes — backup sync and restoration verified manually by the Developer Yes Passed
VR-11 Software Requirements Specification Yes Yes Yes — scaling note explains granularity choice Yes Passed
VR-12 Software Design Yes Yes Yes Yes Passed
VR-13 Traceability Record Yes Yes Yes Yes Passed
VR-14 Software Components Yes Yes Yes Yes Passed
VR-15 Test Cases and Test Procedures Yes Yes Yes — all 34 cases executed and passed 10/08/26–14/08/26 Yes Passed
VR-16 Test Report Yes Yes Yes — records 34 of 34 executed and passed 10/08/26–14/08/26 Yes Passed
VR-17 Software Yes Yes Yes Yes Passed
VR-18 Software User Documentation Yes Yes N/A (forward-facing usage guide) Yes Passed
VR-19 Product Operation Guide Yes Yes Yes Yes Passed
VR-20 Maintenance Documentation Yes Yes Yes Yes Passed

3. Round 2B — Technical work-product verification

ID Verification performed Responsible reviewer Result
TV-01 Customer Requirements are complete, internally consistent, feasible within the agreed project scope, and expressed in a testable form. Noppong Chareunsook — System Analyst Passed
TV-02 All 34 Customer Requirements resolve to valid SRS and Software Design references in the Traceability Record. Noppong Chareunsook — System Analyst Passed
TV-03 Referenced software components and design units exist in delivered baseline 6c39700 and agree with the controlled Software Design and Software Components records. Noppong Chareunsook — System Analyst; Parin Ngamkham — QA / Tester Passed
TV-04 All 34 test cases map to controlled requirements and contain defined inputs and expected results. Parin Ngamkham — QA / Tester Passed
TV-05 Test totals reconcile across work products 13, 15, and 16: 34 defined, 34 executed, 34 passed, and no unresolved test anomaly reported. Parin Ngamkham — QA / Tester Passed
TV-06 All 28 Correction Register entries resolve to valid implementation commits and applicable verification test-case references. Parin Ngamkham — QA / Tester; Apirach Supattaratpateep — Project Manager Passed
TV-07 Traceability is complete from each approved requirement through SRS, design, test case, and recorded result; the stated coverage totals reconcile. Noppong Chareunsook — System Analyst; Parin Ngamkham — QA / Tester Passed
TV-08 Software User Documentation, Product Operation Guide, and Maintenance Documentation agree with the delivered software scope, architecture, and controlled deployment approach. Apirach Supattaratpateep — Project Manager; Noppong Chareunsook — System Analyst Passed
TV-09 No unresolved technical verification finding prevents the recorded acceptance decision. Apirach Supattaratpateep — Project Manager Passed

4. Risk and constraint note

  1. Round 1 was a self-review by the document preparer (the Developer). Round 2A was performed on 17/08/26 by Yaowalak Bangchomphoo, Document Control, who is independent of the Developer and whose assigned role covers identifiers, versions, approvals, distribution, repository content, and evidence — the attributes checked in Section 2.
  2. Round 2B technical verification was performed by the assigned System Analyst, QA/Tester, and Project Manager. Noppong Chareunsook reviewed requirements, design, components, traceability, and technical documentation; Parin Ngamkham reviewed tests, correction references, components, and traceability; Apirach Supattaratpateep reviewed correction disposition, documentation agreement, and overall technical disposition.
  3. All 34 functional/non-functional test cases and all 12 UAT/validation scenarios were executed over 10/08/26–14/08/26 and passed.
  4. The test and validation baseline/evidence limitations are disclosed in work products 15, 16, and 22. Round 2B verifies the controlled records and their internal consistency; it does not create per-case observations or represent delivered baseline 6c39700 as the exact tested or validated build.
  5. Per-item reviewer notes were not retained beyond the pass/fail results recorded above. Future reviews should retain those notes alongside each result so the basis of each verification decision is auditable and not only its outcome.

5. Recommendation

Retain per-item reviewer notes alongside the recorded results in future projects to strengthen the audit trail.

6. Reviewer declarations

By signing the applicable blocks below, the assigned reviewers confirm that they performed the Round 2 checks attributed to their roles, found the referenced work products consistent with the controlled project evidence, recorded the listed checks as Passed, and identified no unresolved verification finding affecting acceptance.

The Document Control signature confirms Round 2A. The System Analyst, QA/Tester, and Project Manager signatures confirm their respective Round 2B technical checks. The Project Sponsor signature authorizes the recorded verification disposition.

7. Approval

Round 2A verified by

Name: Yaowalak Bangchomphoo
Role: Document Control Signature: ______________________________________________
Date: ___________________________________________________

Round 2B requirements, design, components, traceability, and technical documentation verified by

Name: Noppong Chareunsook
Role: System Analyst / Technical Reviewer
Signature: ______________________________________________
Date: ___________________________________________________

Round 2B tests, corrections, components, and traceability verified by

Name: Parin Ngamkham
Role: QA / Tester
Signature: ______________________________________________
Date: ___________________________________________________

Round 2B reviewed and dispositioned by

Name: Apirach Supattaratpateep
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________

Reviewed and authorized by

Name: Seri Viriyasakultorn
Project roles: Project Sponsor / Customer Representative / Authorized Approver