Change Report — Closure Extension
| Document field | Value |
|---|---|
| Document | Change Report |
| Change ID | CH-004 |
| Project | BRN WMS |
| Project code | 200-WMS-26-001-00 |
| Requested and approved date | 17/08/26 |
| Requester | Project Manager / Project Sponsor |
| Change type | Schedule |
| Priority | High |
| Release | 17/08/26 V1.0 |
| Status | Approved — user-confirmed Project Sponsor approval |
Change details
Extend the project closure target from 14/08/26 to 24/08/26. The original period remains the historical baseline and is not overwritten.
Impact analysis
| Area | Impact |
|---|---|
| Schedule | Revised closure target: 24/08/26. |
| Scope | No new functional scope; post-boundary changes remain governed by change control. |
| Evidence | Git commits dated 17/08/26 remain intact and are within the revised closure window. |
| Closure | Independent verification and Project Sponsor acceptance remain required before formal closure. |
Approval
The user confirmed Project Sponsor approval of this schedule extension on 17/08/26. Signature capture remains in the controlled approval sections of the Work Schedule and Acceptance Report.