# Change Report — Closure Extension | Document field | Value | |---|---| | Document | Change Report | | Change ID | CH-004 | | Project | BRN WMS | | Project code | 200-WMS-26-001-00 | | Requested and approved date | 17/08/26 | | Requester | Project Manager / Project Sponsor | | Change type | Schedule | | Priority | High | | Release | 17/08/26 V1.0 | | Status | Approved — user-confirmed Project Sponsor approval | ## Change details Extend the project closure target from 14/08/26 to 24/08/26. The original period remains the historical baseline and is not overwritten. ## Impact analysis | Area | Impact | |---|---| | Schedule | Revised closure target: 24/08/26. | | Scope | No new functional scope; post-boundary changes remain governed by change control. | | Evidence | Git commits dated 17/08/26 remain intact and are within the revised closure window. | | Closure | Independent verification and Project Sponsor acceptance remain required before formal closure. | ## Approval The user confirmed Project Sponsor approval of this schedule extension on 17/08/26. Signature capture remains in the controlled approval sections of the Work Schedule and Acceptance Report.