61 lines
2.4 KiB
Markdown
61 lines
2.4 KiB
Markdown
# Traceability Record Table
|
||
|
||
| Document field | Value |
|
||
|---|---|
|
||
| Document | Traceability Record Table |
|
||
| Project | BRN WMS |
|
||
| Project code | 200-WMS-26-001-00 |
|
||
| Title | Traceability Matrix Summary Table |
|
||
| Project period | 05/01/26–24/08/26 |
|
||
| Release | 17/08/26 V1.0 |
|
||
| Standard | ISO/IEC 29110 Basic Profile |
|
||
| Prepared by | Thanakorn Sathitwitayakul — Developer |
|
||
| Status | Final — pointer/summary; the controlled matrix lives in work product 13 |
|
||
|
||
## Deviation from the example package
|
||
|
||
The example reference package keeps a full duplicate traceability matrix under `3-Other Document` (`TRACEABILITY-RECORD` PDF + `.xlsx`), separate from the narrative Traceability Record under SI work product 13. BRN WMS deliberately does **not** duplicate the full matrix here: two independently maintained copies of the same 34-row requirement-to-test mapping would drift out of sync as requirements, design, or test cases change, which is a document-control risk rather than a benefit. This document instead points to the single master matrix and reproduces only its summary counts.
|
||
|
||
## Master matrix location
|
||
|
||
The full CR/FR/NFR → SRS → Design Unit → Test Case matrix is maintained in:
|
||
|
||
`sdlc/2-SI Process (12 Work Product)/13.Traceability record/200-WMS-26-001-00 Traceability Record 25690817 V1.0.md`
|
||
|
||
## Coverage summary (reproduced from work product 13, Section 4)
|
||
|
||
| Measure | Count |
|
||
|---|---:|
|
||
| Total requirements (FR + NFR) | 34 |
|
||
| Linked to at least one SRS ID | 34 |
|
||
| Linked to at least one Design Unit ID | 34 |
|
||
| Linked to a defined Test Case ID | 34 |
|
||
| Test cases executed with recorded result | 34 |
|
||
| Verified in Verification Results (work product 21) | 0 |
|
||
| Validated in Validation Result (work product 22) | 0 |
|
||
|
||
## Approval
|
||
|
||
### Prepared by
|
||
|
||
Name: Thanakorn Sathitwitayakul
|
||
Role: Developer
|
||
Signature: ______________________________________________
|
||
Date: ___________________________________________________
|
||
|
||
### Reviewed by
|
||
|
||
Name: Apirach Supattaratpateep
|
||
Role: Project Manager
|
||
Signature: ______________________________________________
|
||
Date: ___________________________________________________
|
||
|
||
### Reviewed and authorized by
|
||
|
||
Name: Seri Viriyasakultorn
|
||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||
Position: Managing Director
|
||
Company: B.R.N. Enterprise Co., Ltd.
|
||
Signature: ______________________________________________
|
||
Date: ___________________________________________________
|