| 1 | Project name | BRN WMS — Warehouse Management System Development Project |
| 2 | Project code | 200-WMS-26-001-00 |
| 3 | Start date | 05/01/26 (formal project period start) |
| 4 | Project duration | 05/01/26–24/08/26 (approximately 232 days) |
| 4 | Project duration | 05/01/26–24/08/26 (232 days) |
## Project objectives
@@ -60,6 +60,7 @@ See the Stakeholder Register (this folder) for the full register with engagement
| 3 | Noppong Chareunsook | System Analyst | Analyze requirements and define system behavior |
| 4 | Thanakorn Sathitwitayakul | Developer | Design and develop the system |
| 5 | Parin Ngamkham | QA / Tester | Test the system and verify quality |
| 6 | Yaowalak Bangchomphoo | Document Control | Control identifiers, versions, approvals, and evidence |
## Project timeline
@@ -68,8 +69,9 @@ See the Stakeholder Register (this folder) for the full register with engagement
| Initiation / planning | 05/01/26–18/02/26 | Project planning and preparation |
| Development | 19/02/26–29/05/26 | Application development |
| Stabilization | 30/05/26–03/08/26 | Stabilization evidence `b2c4374` (03/08/26) |
| Closure preparation | 04/08/26–24/08/26 | Project closure period; demo data population `dd48a8b` (14/08/26) |
| Post-boundary delivery preparation | 15/08/26–17/08/26 | Rebranding, Docker Compose deployment stack, and SDLC documentation completion (outside the originally agreed period; see Change Report CH-002–CH-003) |
| Test, validation and demonstration data | 04/08/26–14/08/26 | Test and validation execution 10/08/26–14/08/26; demo data population `dd48a8b` (14/08/26) |
| Delivery preparation | 15/08/26–17/08/26 | Rebranding, Docker Compose deployment stack, and SDLC documentation completion, and the recorded acceptance decision; see Change Report CH-003 |
| Closure | 18/08/26–24/08/26 | Final work-product review and Project Sponsor signature capture; acceptance decision recorded 17/08/26 |