Verification Results

Document field Value
Document Verification Results
Project BRN WMS
Project code 200-WMS-26-001-00
Title Record of Verification Against Standard Requirements
Project period 05/01/26–24/08/26
Release 17/08/26 V1.0
Standard ISO/IEC 29110 Basic Profile
Review round Round 2 completed 17/08/26 — independent verification performed by Yaowalak Bangchomphoo, Document Control
Organizer Apirach Supattaratpateep (Project Manager), Noppong Chareunsook (System Analyst), Thanakorn Sathitwitayakul (Developer)
Round 2 verifier Yaowalak Bangchomphoo — Document Control, independent of the document preparer
Status Final — Round 2 independent verification complete

Objective

Confirm the correctness and completeness of the SDLC work products delivered so far, against ISO/IEC 29110 Basic Profile document-control expectations, before they are treated as ready for Project Sponsor review.

1. Deliverables under review

PM work products 1–10 and SI work products 11–20 (this and work product 22 are excluded, being the verification/validation records themselves).

2. Verification items

Each row checks the document-control header, content, project coverage, and approval block.

ID Work product Header complete Purpose met Evidence basis disclosed Approval block present Result
VR-01 Statement of Work Yes Yes N/A Yes Passed
VR-02 Project Plan (Work Schedule, SPP, Customer Requirements) Yes Yes Yes, where applicable Yes Passed
VR-03 Progress Status Records (13) Yes Yes Yes Yes Passed
VR-04 Correction Register Yes Yes Yes Yes Passed
VR-05 Acceptance Report Yes Yes Yes Yes Passed
VR-06 Change Report (CH-001–CH-003) Yes Yes Yes Yes Passed
VR-07 Meeting Record (MTG-001–MTG-004) Yes Yes Yes — each record discloses its evidence basis and marks unrecorded fields Yes Passed
VR-08 Software Configuration Yes Yes Yes Yes Passed
VR-09 Project Repository Yes Yes Yes Yes Passed
VR-10 Project Repository (Backup) Yes Yes Yes — backup sync and restoration verified manually by the Developer Yes Passed
VR-11 Software Requirements Specification Yes Yes Yes — scaling note explains granularity choice Yes Passed
VR-12 Software Design Yes Yes Yes Yes Passed
VR-13 Traceability Record Yes Yes Yes Yes Passed
VR-14 Software Components Yes Yes Yes Yes Passed
VR-15 Test Cases and Test Procedures Yes Yes Yes — all 34 cases executed and passed 10/08/26–14/08/26 Yes Passed
VR-16 Test Report Yes Yes Yes — records 34 of 34 executed and passed 10/08/26–14/08/26 Yes Passed
VR-17 Software Yes Yes Yes Yes Passed
VR-18 Software User Documentation Yes Yes N/A (forward-facing usage guide) Yes Passed
VR-19 Product Operation Guide Yes Yes Yes Yes Passed
VR-20 Maintenance Documentation Yes Yes Yes Yes Passed

3. Risk and constraint note

  1. Round 1 was a self-review by the document preparer (the Developer). Round 2 was performed on 17/08/26 by Yaowalak Bangchomphoo, Document Control, who is independent of the Developer and whose assigned role covers identifiers, versions, approvals, distribution, repository content, and evidence — the same attributes the verification items in Section 2 check. Per-item reviewer notes were not retained beyond the pass/fail results recorded above.
  2. Test execution, verification, and validation facilitation (work products 15, 16, 22) are now assigned to Parin Ngamkham, QA / Tester, independent of the Developer who prepared this record. This mitigates the self-testing concern for those three work products specifically. Round 1 of this record and of work products 1–14 and 17–21 was a self-review by the Developer who authored them; that self-review was superseded by the Round 2 independent verification performed by Document Control on 17/08/26.
  3. All 34 functional/non-functional test cases and all 12 UAT/validation scenarios were executed over 10/08/26–14/08/26 and passed.
  4. Future reviews should retain per-item reviewer notes alongside the pass/fail result, so the basis of each verification decision is auditable and not only its outcome.

4. Recommendation

Retain per-item reviewer notes alongside the recorded results in future projects to strengthen the audit trail.

5. Approval

Prepared by (Round 2 independent verification)

Name: Yaowalak Bangchomphoo
Role: Document Control Signature: ______________________________________________
Date: ___________________________________________________

Reviewed by

Name: Apirach Supattaratpateep
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________

Reviewed and authorized by

Name: Seri Viriyasakultorn
Project roles: Project Sponsor / Customer Representative / Authorized Approver
Position: Managing Director
Company: B.R.N. Enterprise Co., Ltd.
Signature: ______________________________________________
Date: ___________________________________________________