List of Evidence

Document field Value
Document List of Evidence
Project BRN WMS
Project code 200-WMS-26-001-00
Title Record of Verification of Project Document Preparation and Storage Status
Project period 05/01/26–24/08/26
Release 17/08/26 V1.0
Standard ISO/IEC 29110 Basic Profile
Organizer Apirach Supattaratpateep (Project Manager), Noppong Chareunsook (System Analyst), Thanakorn Sathitwitayakul (Developer)
Status Final — reflects the document inventory at project baseline

Objective

Index every controlled work product prepared for BRN WMS, its file, and its current preparation status, so completeness can be checked at a glance without opening each folder.

Standards basis and applicability

This evidence index covers the ISO/IEC 29110 software engineering Generic Basic Profile for one non-safety-critical software product developed by one project team under a customer project agreement. The project applies ISO/IEC 29110-4-1:2018 as the Generic Basic-profile specification and ISO/IEC 29110-5-1-2:2025 as the applicable management and software engineering guideline. The authoritative applicability and tailoring statement is maintained in the Software Project Plan, Sections 1.1 and 1.2.

Applicability item BRN WMS application
Profile Generic Basic profile — software engineering
Product/team model One software product developed by one project team
Safety criticality Non-safety-critical
Processes evidenced Project Management and Software Implementation
Lifecycle Incremental/evolutionary with controlled baselines
Controlled source/output Markdown under sdlc/; generated printing/delivery PDFs under sdlc-delivery/

The work-product structure is tailored as follows: Project Plan content spans the Work Schedule, Software Project Plan, and Customer Requirements; work product 17 identifies the Git-controlled software baseline; work product 13 is the single master traceability matrix; Test Cases and Test Procedures also records execution status; and the Other Document items supplement rather than replace the 22 PM/SI work products.

Basic-profile activity-to-evidence conformity matrix

ISO/IEC 29110 activity Activity purpose Responsible BRN WMS roles Controlled BRN WMS evidence Result
PM.1 Project Planning Review the agreement and establish scope, tasks, schedule, resources, risks, responsibilities, and project controls. Project Manager; Customer Representative; System Analyst Statement of Work; Work Schedule; Software Project Plan; Customer Requirements Conforms
PM.2 Project Plan Execution Direct assigned work, monitor progress, communicate status and decisions, and maintain controlled project records. Project Manager; Work Team; Customer Representative 13 Progress Status Records; Meeting Records; Project Repository; Work Schedule Conforms
PM.3 Project Assessment and Control Assess performance and deviations, and control corrections, changes, risks, issues, and configuration items. Project Manager; Developer; QA / Tester; Document Control Progress Status Records; Correction Register; Change Reports; Software Configuration; Verification Results Conforms
PM.4 Project Closure Confirm delivery, acceptance, repository completion, backup, and authorized project closure. Project Manager; Customer Representative; Developer Acceptance Report; Project Repository; Project Repository (Backup); List of Evidence; final Progress Status Record Conforms
SI.1 Software Implementation Initiation Establish the implementation approach, assignments, environment, repository, and controlled starting baseline. Project Manager; System Analyst; Developer Software Project Plan; Software Configuration; Project Repository; Work Schedule Conforms
SI.2 Software Requirements Analysis Analyze agreed customer needs, define software requirements, verify them, and maintain bidirectional traceability. System Analyst; Customer Representative; QA / Tester Customer Requirements; Software Requirements Specification; Traceability Record; Verification Results Conforms
SI.3 Software Architectural and Detailed Design Define architecture, components, interfaces, data design, and software units consistent with requirements. System Analyst; Developer; QA / Tester Software Design; Software Components; Traceability Record; Verification Results Conforms
SI.4 Software Construction Implement, review, correct, and control the software components that realize the approved design. Developer; System Analyst; QA / Tester Git baseline; Software Components; Software record; Correction Register; Change Reports Conforms
SI.5 Software Integration and Tests Integrate components, define and execute tests, resolve anomalies, and record verification results. Developer; QA / Tester; Project Manager Test Cases and Test Procedures; Test Report; Correction Register; Traceability Record; Verification Results Conforms
SI.6 Product Delivery Deliver the controlled software and supporting documentation, validate intended use, and obtain customer acceptance. Project Manager; Customer Representative; Developer; QA / Tester Software record; Software User Documentation; Product Operation Guide; Maintenance Documentation; Validation Result; Acceptance Report Conforms

This matrix identifies how the controlled BRN WMS evidence demonstrates execution of the ISO/IEC 29110 Generic Basic-profile Project Management and Software Implementation activities. Conforms means that the applicable activity is represented by controlled, reviewed, and signed project evidence. Document presence alone is not treated as proof of conformity; the result relies on the content, cross-references, role-specific reviews, verification, validation, and authorization recorded in the referenced work products.

PM Process

No. Work product File(s) Status
1 Statement of Work 200-WMS-26-001-00 Statement of Work 25690105 V1.0 Final.md Complete (Markdown, HTML, PDF)
2 Project Plan — Work Schedule 200-WMS-26-001-00 Work Schedule 25690817 V1.0 Final.md Complete
2 Project Plan — Software Project Plan 200-WMS-26-001-00 Software Project Plan 25690817 V1.0 Final.md Complete
2 Project Plan — Customer Requirements 200-WMS-26-001-00 Customer Requirements 25690112 V1.0 Final.md Complete
3 Progress Status Record (13 records) ...25690123, 25690218, 25690225, 25690317, 25690429, 25690508, 25690513, 25690523, 25690529, 25690731, 25690803, 25690814, 25690817 V1.0.md Complete (all 13)
4 Correction Register 200-WMS-26-001-00 Correction Register 25690817 V1.0.md Complete; 28 entries, all verified against linked test cases and formally closed
5 Acceptance Report 200-WMS-26-001-00 Acceptance Report 25690817 V1.0.md Complete; decision Accepted; all acceptance conditions closed
6 Change Report (3 separate reports) ... - Rack to Bin Rename 25690521, - Demo Data Population 25690808, - Delivery Preparation Bundle 25690810 Complete (CH-001–CH-003)
7 Meeting Record (4 checkpoint records) ... - Project Initiation Checkpoint 25690213, - Development Substantially Complete Checkpoint 25690529, - Stabilization Checkpoint 25690803, - Closure Preparation Checkpoint 25690814 Complete (MTG-001–MTG-004)
8 Software Configuration 200-WMS-26-001-00 Software Configuration 25690817 V1.0.md Complete
9 Project Repository 200-WMS-26-001-00 Project Repository 25690817 V1.0.md Complete
10 Project Repository (Backup) 200-WMS-26-001-00 Project Repository (Backup) 25690817 V1.0.md Backup mechanism and restoration check complete; final SDLC delivery-branch synchronization tracked as BK-004

SI Process

No. Work product File Status
11 Software Requirements Specification (SRS) 200-WMS-26-001-00 Software Requirements Specification 25690817 V1.0.md Complete
12 Software Design 200-WMS-26-001-00 Software Design 25690817 V1.0.md Complete
13 Traceability Record 200-WMS-26-001-00 Traceability Record 25690817 V1.0.md Complete; 34/34 requirements linked and verified
14 Software Components 200-WMS-26-001-00 Software Components 25690817 V1.0.md Complete
15 Test Cases and Test Procedures 200-WMS-26-001-00 Test Cases and Test Procedures 25690817 V1.0.md Complete; 34 cases defined, 34 executed 10/08/26–14/08/26
16 Test Report 200-WMS-26-001-00 Test Report 25690817 V1.0.md Complete; 34 of 34 passed
17 Software 200-WMS-26-001-00 Software 25690817 V1.0.md Markdown complete (pointer record); the software itself is delivered via the Git repository
18 Software User Documentation 200-WMS-26-001-00 Software User Documentation 25690817 V1.0.md Complete
19 Product Operation Guide 200-WMS-26-001-00 Product Operation Guide 25690817 V1.0.md Complete; operational follow-up actions include targets and closure criteria
20 Maintenance Documentation 200-WMS-26-001-00 Maintenance Documentation 25690817 V1.0.md Complete
21 Verification Results 200-WMS-26-001-00 Verification Results 25690817 V1.0.md Complete; Round 2A document-control and Round 2B technical work-product verification completed 17/08/26
22 Validation Result 200-WMS-26-001-00 Validation Result 25690817 V1.0.md Complete; 12 of 12 scenarios passed

Other Document

No. Item File Status
1 List of Evidence This document Complete
2 Stakeholder Register 200-WMS-26-001-00 Stakeholder Register 25690817 V1.0.md Complete
3 Project Charter Report 200-WMS-26-001-00 Project Charter Report 25690817 V1.0.md Complete
4 Traceability Record Table 200-WMS-26-001-00 Traceability Record Table 25690817 V1.0.md Complete as a pointer/summary to work product 13 (single master matrix; see that document for the deviation rationale)
5 Training Report 200-WMS-26-001-00 Training Report 25690817 V1.0.md Not yet conducted; planned curriculum only

Summary

Measure Count
Total controlled work-product entries (PM + SI, counting each grouped item as one row above) 22
Total individual controlled files (13 Progress Status Records + 3 Change Reports + 4 Meeting Records + 26 single-instance documents) 46
Basic-profile activities mapped to controlled evidence 10 of 10 (PM.1–PM.4 and SI.1–SI.6)
Markdown source complete under sdlc/ 46 of 46
Included in the generated PDF delivery package (sdlc-delivery/) 46 of 46, including all 4 Meeting Records
Other Document items complete 4 of 5 (Training Report pending execution, not preparation)

The PDF delivery package is generated from sdlc/ by scripts/build-sdlc-delivery.sh; it is build output and is not edited by hand.

Approval

Prepared by

Name: Thanakorn Sathitwitayakul
Role: Developer Signature: ______________________________________________
Date: ___________________________________________________

Reviewed by

Name: Apirach Supattaratpateep
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________

Reviewed and authorized by

Name: Seri Viriyasakultorn
Project roles: Project Sponsor / Customer Representative / Authorized Approver
Position: Managing Director
Company: B.R.N. Enterprise Co., Ltd.
Signature: ______________________________________________