Training Report
| Document field | Value |
|---|---|
| Document | Training Report |
| Project | BRN WMS |
| Project code | 200-WMS-26-001-00 |
| Title | รายงานอบรม (Training Report) |
| Project period | 05/01/26–24/08/26 |
| Preparation date | 17/08/26 |
| Release | 17/08/26 V1.0 |
| Standard | ISO/IEC 29110 Basic Profile |
| Prepared by | คุณอภิรัชต์ สุภัทรประทีป — Project Manager |
| Status | Final as a status report — no training session has been conducted; see Section 1 |
1. Disclosure
At report preparation (17/08/26), no user-training session has taken place for BRN WMS. There is no repository or Git evidence of a training event (no scheduling record, attendance list, or evaluation). Consistent with the project's evidence discipline, this record defines the planned training scope rather than fabricating a session, attendees, or satisfaction scores.
2. Planned training information
| หัวข้อ | รายละเอียด |
|---|---|
| วันที่อบรม (Date) | Not yet scheduled |
| สถานที่ (Location) | Not yet determined |
| วิทยากรผู้สอน (Trainer) | ธนกร สถิตวิทยากุล (Developer / System Analyst); no dedicated trainer role is currently assigned |
| ผู้จัดโครงการอบรม (Organizer) | คุณอภิรัชต์ สุภัทรประทีป (Project Manager) |
| จำนวนผู้เข้าอบรม (Expected attendance) | Not yet determined — expected to include Owner/Admin, Staff, and Viewer role representatives per company |
3. Planned curriculum
Derived from the Software User Documentation (work product 18):
| No. | Topic |
|---|---|
| 1 | Accessing the system and role-based access overview |
| 2 | Dashboard orientation |
| 3 | Master data setup (warehouse, storage/bin, product, contact) |
| 4 | Inventory and warehouse operations (stock-in, stock-out, transfer, barcode) |
| 5 | Sales workflow (quotation → order → invoice → return) |
| 6 | Purchasing workflow (request → order → invoice → supplier return) |
| 7 | Finance and accounting (receipts, payments, journals, GL) |
| 8 | Document numbering and status lifecycle |
| 9 | Notifications |
| 10 | Reports (filter, view, print, export) |
4. Result
No result to report — training has not yet occurred. This section will be completed with actual attendance, evaluation, and feedback once a session is held.
5. Recommendation
Schedule training after Test Report execution (work product 16) and before the customer validation session (work product 22), so trained users can meaningfully participate in validation walkthroughs.
6. Approval
Prepared by
Name: คุณอภิรัชต์ สุภัทรประทีป
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________
Reviewed by
Name: ธนกร สถิตวิทยากุล
Role: Developer / System Analyst
Signature: ______________________________________________
Date: ___________________________________________________
Reviewed and authorized by
Name: คุณเสรี วิริยะสกุลธรณ์
Project roles: Project Sponsor / Customer Representative / Authorized Approver
Position: กรรมการผู้จัดการ
Company: บริษัท บี.อาร์.เอ็น. เอ็นเตอร์ไพรส์ จำกัด
Signature: ______________________________________________
Date: ___________________________________________________