Acceptance Report

Document field Value
Document Acceptance Report
Project BRN WMS
Project code 200-WMS-26-001-00
Title Record of System Delivery and Acceptance
Project period 05/01/26–24/08/26
Delivery date 17/08/26
Release 17/08/26 V1.0 Final
Standard ISO/IEC 29110 Basic Profile
Delivering Project Manager Apirach Supattaratpateep
Technical delivery Thanakorn Sathitwitayakul — Developer
Receiving authority Seri Viriyasakultorn — Project Sponsor / Customer Representative / Authorized Approver
Document status Final
Acceptance decision Accepted

1. Purpose

This Acceptance Report records BRN WMS delivery against the agreed scope and the project acceptance decision. The delivery date of 17/08/26 is the date the final delivery-preparation change (CH-003) was completed and the acceptance decision was recorded; the formal project end date is 24/08/26.

2. Delivered system scope

The delivery comprises the implemented browser-based BRN WMS application and supporting components for:

  • Company, user, role, application access, SMTP, and system configuration.
  • Contact, product, category, warehouse, storage, and bin master data.
  • Stock-in, stock-out, stock transfer, balances, lot, serial, expiry, occupancy, and movement reporting.
  • SKU and location barcode labels and supported scanning workflows.
  • Quotation, sales order, invoice, return, and credit-note workflows.
  • Purchase request, purchase order, purchase invoice, and supplier-return workflows.
  • Receipt billing, receipts, payment billing, and payments.
  • Chart of accounts, departments, journals, general ledger, formulas, and financial reports.
  • Controlled document numbering and lifecycle/status handling.
  • Node.js/Socket.IO notifications and scheduled stock/GL maintenance and alerts.
  • Deployment configuration and automated database setup capability.

3. Delivery package status

No. Delivery item Expected evidence Current result Acceptance state
1 BRN WMS source code Controlled Git repository and final commit history Repository exists; implementation history available Delivered; repository baseline reviewed
2 Database setup/schema setup.php, configuration guidance, and database definitions Setup implementation and configuration guide available Delivered; installation verified via TC-NFR-004
3 Node.js services Notification and scheduler source/configuration Source and configuration examples available Delivered; operational behaviour verified via TC-FR-021, TC-FR-022
4 Statement of Work 200-WMS-26-001-00 V1.0 Final Completed Pending Project Sponsor signature
5 Project Plan Work Schedule, Software Project Plan, and Customer Requirements Completed as V1.0 Final Pending Project Sponsor authorization
6 Progress Status Records 13 task-based period records Complete Accepted
7 Correction Register Corrections and status 28 corrections recorded Accepted
8 Software Requirements Specification Approved BRN WMS SRS Complete Accepted
9 Software Design Approved BRN WMS design Approved V1.0 (work product 12) Reviewed in Round 2 verification 17/08/26; Sponsor signature outstanding
10 Traceability Record Requirements-to-design-code-test-result mapping V1.0 (work product 13); all 34 requirements linked to SRS/Design/Test Case IDs Complete; 34 of 34 requirements verified
11 Test Cases and Test Procedures Controlled functional and non-functional tests V1.0 (work product 15); 34 cases defined, responsible role Parin Ngamkham (QA/Tester) 34 of 34 executed and passed 10/08/26–14/08/26
12 Test Report Executed results and defect disposition V1.0 (work product 16) as a status report 34 of 34 executed and passed 10/08/26–14/08/26
13 Verification Results Reviewed work-product verification evidence V1.0 (work product 21); Round 2 independent verification Round 2 independent verification performed by Document Control 17/08/26
14 Validation Results Customer-oriented intended-use evidence V1.0 (work product 22); 12 scenarios defined 12 of 12 executed and passed with customer 10/08/26–14/08/26
15 User Documentation BRN WMS user guide V1.0 (work product 18) Reviewed in Round 2 verification 17/08/26
16 Product Operation Guide Deployment, operation, monitoring, backup, and recovery V1.0 (work product 19); includes install, config, monitoring, and backup sections Reviewed in Round 2 verification 17/08/26; backup restoration verified manually (OP-001 retains a documentation-detail item only)
17 Maintenance Documentation Architecture, components, configuration, known issues, and maintenance process V1.0 (work product 20) Reviewed in Round 2 verification 17/08/26
18 Repository backup Backup record and restoration check Repository exists; backup Git remote in sync and a daily mysqldump script, both verified manually by the Developer Satisfied; restoration check performed (BK-001, BK-002 closed)

4. Acceptance criteria status

ID Acceptance criterion Evidence required Current assessment
AC-001 All acceptance-critical requirements are implemented. Approved requirements and complete traceability Satisfied; traceability complete (34/34 linked, work product 13) with all 34 linked test cases executed and passed
AC-002 Representative warehouse, sales, purchasing, finance, and accounting workflows pass. Approved Test Report and Validation Results Satisfied; Test Report 34 of 34 passed and Validation Result 12 of 12 passed, executed 10/08/26–14/08/26
AC-003 No unresolved critical defect remains. Correction Register linked to verification results Satisfied; all 28 corrections verified against linked test cases; no unresolved critical defect
AC-004 Security, role, tenant, and warehouse isolation controls pass negative tests. Security and authorization test results Satisfied; TC-NFR-002 and TC-FR-024 executed and passed 10/08/26–14/08/26
AC-005 Installation and configuration are repeatable in the supported environment. Installation execution record Satisfied; installation, configuration, backup and restoration all exercised via TC-NFR-004
AC-006 User, operation, and maintenance documentation is complete. Reviewed controlled guides Satisfied; work products 18–20 reviewed in Round 2 verification 17/08/26
AC-007 Source, software, documents, and evidence are stored in the controlled repository and backup. Repository inventory and restore-check record Satisfied; repository and documents controlled, backup mechanisms documented and restoration verified
AC-008 Project Sponsor confirms intended use and authorizes acceptance. Signed Validation Results and Acceptance Report Decision recorded as Accepted on user confirmation 17/08/26; Sponsor signature capture outstanding

5. Requirements acceptance summary

The Customer Requirements contain 24 functional and 10 non-functional requirements. At project baseline:

Measure Count / state
Customer requirements 34
Requirements with completed forward traceability (SRS/Design/Test Case linked) 34 of 34 (work product 13)
Requirements with independently reviewed/approved traceability 34
Requirements with executed, recorded test results 34
Requirements formally accepted 34, subject to Sponsor signature capture

Independent review, test execution, and customer validation were completed over 10/08/26–14/08/26 and confirmed by the project user on 17/08/26. Sponsor signature capture on the controlled records remains an administrative follow-up.

6. Correction and issue status

Measure Count
Corrections recorded 28
Verified against linked test cases 28
Covered by Round 2 verification (17/08/26) 28
Formally closed (awaiting Sponsor signature) 0

Formal acceptance must not rely solely on corrective commits. Each applicable correction must link to a requirement/component, test result, and closure decision.

7. Acceptance conditions and their status

Condition ID Required action Owner Status
CON-001 Independently review and approve the Software Requirements Specification (work product 11). Project Manager / Project Sponsor Completed — Round 2 verification 17/08/26 (VR-11)
CON-002 Independently review and approve the Software Design (work product 12). Project Manager / Project Sponsor Completed — Round 2 verification 17/08/26 (VR-12)
CON-003 Independently verify the Traceability Record (work product 13, 34/34 requirements linked) against executed test results. QA/Tester / Project Manager Completed — 34 of 34 verified against results executed 10/08/26–14/08/26
CON-004 Execute the 34 defined test cases (work product 15) and record results in the Test Report (work product 16). QA/Tester (Parin Ngamkham) Completed — 34 of 34 executed and passed 10/08/26–14/08/26
CON-005 Verify corrections and close or disposition all acceptance-critical defects. QA/Tester / Project Manager Completed — all 28 corrections verified against linked test cases; formal closure awaits CON-009
CON-006 Independent Round 2 verification and the 12 validation/UAT scenarios. Document Control / Customer Representative Completed — Round 2 by Yaowalak Bangchomphoo and UAT by Seri Viriyasakultorn, 17/08/26
CON-007 Independently review the User Documentation, Product Operation Guide, and Maintenance Documentation (work products 18–20). Project Manager / Document Control Completed — Round 2 verification 17/08/26 (VR-18 to VR-20)
CON-008 Verify the backup remote is in sync and perform a restoration check (work product 10). Developer Completed — both performed manually by the Developer (BK-001, BK-002 closed)
CON-009 Obtain Project Sponsor signatures on required controlled work products. Project Manager / Project Sponsor Open — signature capture outstanding

One condition remains open: CON-009, Project Sponsor signature capture, which is administrative record capture and does not block operational use of the delivered system. A documentation-detail item (Product Operation Guide OP-001) remains to record the manual backup's schedule, location and retention in a controlled reference.

Recommended decision at 17/08/26: Accepted.

The project user confirmed that the required reviews, the 34 test cases and 12 validation/UAT scenarios executed over 10/08/26–14/08/26, correction disposition, and Project Sponsor authorization are complete. This supports an Accepted decision. One condition remains open and is recorded in Section 7: Sponsor signature capture (CON-009).

9. Acceptance decision options

The Project Sponsor shall select one option:

  • Accepted — All mandatory acceptance criteria are satisfied by user confirmation; CON-009 (signature capture) remains open per Section 7.
  • Accepted with conditions — The system may be used subject to the conditions and deadlines recorded below.
  • Not accepted — Mandatory criteria are not satisfied; correction and re-submission are required.
  • Decision pending — Review/evidence is incomplete and no acceptance decision has yet been signed.

Conditions, exceptions, or rejection reasons:



Required completion date for accepted conditions: ________________________________

10. Delivery and acceptance authorization

Delivered by

Name: Apirach Supattaratpateep
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________

Technical delivery confirmed by

Name: Thanakorn Sathitwitayakul
Role: Developer Signature: ______________________________________________
Date: ___________________________________________________

Received and decided by

Name: Seri Viriyasakultorn
Project roles: Project Sponsor / Customer Representative / Authorized Approver
Position: Managing Director
Company: B.R.N. Enterprise Co., Ltd.
Decision: Accepted / Accepted with conditions / Not accepted
Signature: ______________________________________________
Date: ___________________________________________________