Project Repository (Backup)
| Document field | Value |
|---|---|
| Document | Project Repository (Backup) |
| Project | BRN WMS |
| Project code | 200-WMS-26-001-00 |
| Title | Project Repository Backup Record |
| Project period | 05/01/26–24/08/26 |
| Release | 17/08/26 V1.0 |
| Standard | ISO/IEC 29110 Basic Profile |
| System Analyst | Noppong Chareunsook |
| Developer | Thanakorn Sathitwitayakul |
| Project Manager | Apirach Supattaratpateep |
| Project Sponsor / Customer Representative | Seri Viriyasakultorn |
| Status | Final |
1. Purpose
This record identifies the backup mechanisms protecting BRN WMS source code and SDLC work products against loss of the primary repository, per the Project Repository record (Section 2).
2. Code backup
| Field | Value |
|---|---|
| Backup mechanism | Secondary Git remote |
| Backup remote name | backup |
| Backup remote URL | git@github.com:thanakorninbox-dev/wms-app.git |
| Configuration | Secondary remote is configured for origin/main. |
| Sync status | Maintained by the Developer; confirmed in sync with origin/main. |
| Restoration check | Performed manually by the Developer and confirmed successful. Carried out outside version control, so no Git artefact records it. |
3. Document backup
| Field | Value |
|---|---|
| Backup mechanism | Exported PDF package, external to the Git repository |
| Location | sdlc-delivery/ in the repository, generated from sdlc/ by scripts/build-sdlc-delivery.sh |
| Contents | 42 PDFs covering the PM, SI, and Other Document work products; regeneration pending for the 4 Meeting Records |
| Verification | Verified as non-empty and readable |
4. Backup verification items
| ID | Item | Owner | Required before |
|---|---|---|---|
| BK-001 | Confirm the backup remote is reachable and up to date with origin/main. |
Developer | Closed — confirmed by the Developer |
| BK-002 | Perform and record a restoration check (clone from backup and verify integrity). |
Developer | Closed — performed manually by the Developer |
| BK-003 | Regenerate the PDF delivery package so it covers all 46 controlled files (the 4 Meeting Records are not yet included). | Developer | Final delivery |
5. Approval
Prepared by
Name: Thanakorn Sathitwitayakul
Role: Developer
Signature: ______________________________________________
Date: ___________________________________________________
Reviewed by
Name: Apirach Supattaratpateep
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________
Reviewed and authorized by
Name: Seri Viriyasakultorn
Project roles: Project Sponsor / Customer Representative / Authorized Approver
Position: Managing Director
Company: B.R.N. Enterprise Co., Ltd.
Signature: ______________________________________________
Date: ___________________________________________________