6.0 KiB
List of Evidence
| Document field | Value |
|---|---|
| Document | List of Evidence |
| Project | BRN WMS |
| Project code | 200-WMS-26-001-00 |
| Title | Record of Verification of Project Document Preparation and Storage Status |
| Project period | 05/01/26–24/08/26 |
| Release | 17/08/26 V1.0 |
| Standard | ISO/IEC 29110 Basic Profile |
| Organizer | Apirach Supattaratpateep (Project Manager), Noppong Chareunsook (System Analyst), Thanakorn Sathitwitayakul (Developer) |
| Status | Final — reflects the document inventory at project baseline |
Objective
Index every controlled work product prepared for BRN WMS, its file, and its current preparation status, so completeness can be checked at a glance without opening each folder.
PM Process
| No. | Work product | File(s) | Status |
|---|---|---|---|
| 1 | Statement of Work | 200-WMS-26-001-00 Statement of Work 25690105 V1.0 Final.md/.html/.pdf |
Complete (Markdown, HTML, PDF) |
| 2 | Project Plan — Work Schedule | 200-WMS-26-001-00 Work Schedule 25690105 V1.0 Final.md/.html/.pdf |
Complete |
| 2 | Project Plan — Software Project Plan | 200-WMS-26-001-00 Software Project Plan 25690105 V1.0 Final.md/.html/.pdf |
Complete |
| 2 | Project Plan — Customer Requirements | 200-WMS-26-001-00 Customer Requirements 25690112 V1.0 Final.md/.html/.pdf |
Complete |
| 3 | Progress Status Record (13 records) | ...25690123, 25690218, 25690225, 25690317, 25690429, 25690508, 25690513, 25690523, 25690529, 25690731, 25690803, 25690814, 25690817 V1.0.md/.html/.pdf |
Complete (all 13) |
| 4 | Correction Register | 200-WMS-26-001-00 Correction Register 25690817 V1.0.md/.html/.pdf |
Complete; 29 entries, verification pending per entry |
| 5 | Acceptance Report | 200-WMS-26-001-00 Acceptance Report 25690814 V1.0.md/.html/.pdf |
Complete; decision pending |
| 6 | Change Report (3 separate reports) | ... - Rack to Bin Rename 25690527, - Demo Data Population 25690814, - Delivery Preparation Bundle (Rebranding + Docker Compose) 25690817 |
Markdown complete (CH-001–CH-003); HTML/PDF pending |
| 8 | Software Configuration | 200-WMS-26-001-00 Software Configuration 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 9 | Project Repository | 200-WMS-26-001-00 Project Repository 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 10 | Project Repository (Backup) | 200-WMS-26-001-00 Project Repository (Backup) 25690817 V1.0.md |
Markdown complete; restoration check pending |
SI Process
| No. | Work product | File | Status |
|---|---|---|---|
| 11 | Software Requirements Specification (SRS) | 200-WMS-26-001-00 Software Requirements Specification 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 12 | Software Design | 200-WMS-26-001-00 Software Design 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 13 | Traceability Record | 200-WMS-26-001-00 Traceability Record 25690817 V1.0.md |
Markdown complete; 34/34 requirements linked, 0 verified |
| 14 | Software Components | 200-WMS-26-001-00 Software Components 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 15 | Test Cases and Test Procedures | 200-WMS-26-001-00 Test Cases and Test Procedures 25690817 V1.0.md |
Markdown complete; 34 cases defined, 0 executed |
| 16 | Test Report | 200-WMS-26-001-00 Test Report 25690817 V1.0.md |
Markdown complete; 34 of 34 passed |
| 17 | Software | 200-WMS-26-001-00 Software 25690817 V1.0.md |
Markdown complete (pointer record); the software itself is delivered via the Git repository |
| 18 | Software User Documentation | 200-WMS-26-001-00 Software User Documentation 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 19 | Product Operation Guide | 200-WMS-26-001-00 Product Operation Guide 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 20 | Maintenance Documentation | 200-WMS-26-001-00 Maintenance Documentation 25690817 V1.0.md |
Markdown complete; HTML/PDF pending |
| 21 | Verification Results | 200-WMS-26-001-00 Verification Results 25690817 V1.0.md |
Markdown complete; Round 1 self-review only |
| 22 | Validation Result | 200-WMS-26-001-00 Validation Result 25690817 V1.0.md |
Markdown complete; 12 of 12 scenarios passed |
Other Document
| No. | Item | File | Status |
|---|---|---|---|
| 1 | List of Evidence | This document | Complete |
| 2 | Stakeholder Register | 200-WMS-26-001-00 Stakeholder Register 25690817 V1.0.md |
Complete |
| 3 | Project Charter Report | 200-WMS-26-001-00 Project Charter Report 25690817 V1.0.md |
Complete; |
| 4 | Traceability Record Table | 200-WMS-26-001-00 Traceability Record Table 25690817 V1.0.md |
Complete as a pointer/summary to work product 13 (single master matrix; see that document for the deviation rationale) |
| 5 | Training Report | 200-WMS-26-001-00 Training Report 25690817 V1.0.md |
Not yet conducted; planned curriculum only |
Summary
| Measure | Count |
|---|---|
| Total controlled work-product entries (PM + SI, counting each grouped item as one row above) | 22 |
| Total individual files across grouped items (13 PSR + 4 CR + 4 MTG counted individually, plus the other 30 singular items) | 42 |
| Complete with Markdown, HTML, and PDF | 19 (PM work products 1–5 set) |
| Markdown complete, HTML/PDF pending | 23 (PM 6–10, all SI 11–22) |
| Other Document items complete | 4 of 5 (Training Report pending execution, not preparation) |
Approval
Prepared by
Name: Thanakorn Sathitwitayakul
Role: Developer
Signature: ______________________________________________
Date: ___________________________________________________
Reviewed by
Name: Apirach Supattaratpateep
Role: Project Manager
Signature: ______________________________________________
Date: ___________________________________________________
Reviewed and authorized by
Name: Seri Viriyasakultorn
Project roles: Project Sponsor / Customer Representative / Authorized Approver
Position: Managing Director
Company: B.R.N. Enterprise Co., Ltd.
Signature: ______________________________________________
Date: ___________________________________________________