# BRN WMS (200-WMS-26-001-00) — ISO/IEC 29110 audit preparation ## 1. Questions auditors usually ask ### Project Management (PM) | Usual question | Where to point | |---|---| | What was agreed with the customer: scope, deliverables, acceptance criteria? | Statement of Work, Software Project Plan §3 | | How did you plan: tasks, people, effort, schedule? | Work Schedule, Software Project Plan §5–8 | | How did you track progress, and what did you do when something slipped? | Progress Status Records (15 periods), Minutes of Meeting | | What risks did you identify, and were they reviewed? | Software Project Plan §9 (R1–R8); expect "show me a risk that changed during the project" | | How were changes requested, assessed and approved? | Change Report | | How were defects recorded and closed? | Correction Register ISS-001–028, each linked to a commit and a test case | | How is the repository controlled and backed up? | Project Repository, Project Repository (Backup), Software Configuration (`main`, baseline `6c39700`) | | Did the customer formally accept the product? | Acceptance Report, Validation Results | ### Software Implementation (SI) | Usual question | Where to point | |---|---| | Were requirements reviewed and baselined before development? | Customer Requirements (CR01–CR14), SRS (SR01–SR09), requirements baseline 18 Feb 2569 | | Pick one requirement and show its design, code, test and result | Traceability Record — most common test; rehearse 2–3 requirements end to end | | Show the design and how it maps to the code | Software Design (units UN01–UN13 with file paths) | | Who reviewed which documents, what was found, and how was it fixed? | Verification Results V0.1–V1.0 (4 rounds) | | Show the test cases and test results, including a failure and its retest | Test Case and Test Procedures (45), Test Report, Correction Register | | What exactly was delivered, and can you rebuild it? | Software, Software Components, Product Operation Guide | | Are user, operation and maintenance documents available? | Software User Document, Product Operation Guide, Maintenance Document | ### Weak points likely to be probed | Point | How to prepare | |---|---| | No change requests in 8 months | Explain why the evaluated items did not meet the change criteria | | All 45 test cases passed in one run | Point to the Correction Register: defects were found and fixed during development | | Risks never re-rated | Be ready to show where risks were reviewed in Progress Status Records | | Interviews must match the documents | Developer and QA rehearse: how a defect is logged; how TC-UN08.002 was run |