# Acceptance Report | Document field | Value | |---|---| | Document | Acceptance Report | | Project | BRN WMS | | Project code | 200-WMS-26-001-00 | | Title | Record of System Delivery and Acceptance | | Project period | 05/01/26–24/08/26 | | Delivery date | 17/08/26 | | Release | 17/08/26 V1.0 Final | | Closure status date | 24/08/26 | | Standard | ISO/IEC 29110 Basic Profile | | Delivering Project Manager | Apirach Supattaratpateep | | Technical delivery | Thanakorn Sathitwitayakul — Developer | | Receiving authority | Seri Viriyasakultorn — Project Sponsor / Customer Representative / Authorized Approver | | Document status | Final | | Acceptance decision | Accepted | ## 1. Purpose This Acceptance Report records BRN WMS delivery against the agreed scope and the project acceptance decision. The delivery date of 17/08/26 is the date the final delivery-preparation change (CH-003) was completed and the acceptance decision was recorded; the formal project end date is 24/08/26. ## 2. Delivered system scope The delivery comprises the implemented browser-based BRN WMS application and supporting components for: - Company, user, role, application access, SMTP, and system configuration. - Contact, product, category, warehouse, storage, and bin master data. - Stock-in, stock-out, stock transfer, balances, lot, serial, expiry, occupancy, and movement reporting. - SKU and location barcode labels and supported scanning workflows. - Quotation, sales order, invoice, return, and credit-note workflows. - Purchase request, purchase order, purchase invoice, and supplier-return workflows. - Receipt billing, receipts, payment billing, and payments. - Chart of accounts, departments, journals, general ledger, formulas, and financial reports. - Controlled document numbering and lifecycle/status handling. - Node.js/Socket.IO notifications and scheduled stock/GL maintenance and alerts. - Deployment configuration and automated database setup capability. ## 3. Delivery package status | No. | Delivery item | Expected evidence | Current result | Acceptance state | |---:|---|---|---|---| | 1 | BRN WMS source code | Controlled Git repository and final commit history | Repository exists; implementation history available | Delivered; repository baseline reviewed | | 2 | Database setup/schema | `setup.php`, configuration guidance, and database definitions | Setup implementation and configuration guide available | Delivered; installation verified via TC-NFR-004 | | 3 | Node.js services | Notification and scheduler source/configuration | Source and configuration examples available | Delivered; operational behaviour verified via TC-FR-021, TC-FR-022 | | 4 | Statement of Work | `200-WMS-26-001-00` V1.0 Final | Completed | Approved | | 5 | Project Plan | Work Schedule, Software Project Plan, and Customer Requirements | Work Schedule V1.0 Final; Software Project Plan V1.0 Final; Customer Requirements V1.0 Final | Approved | | 6 | Progress Status Records | 13 task-based period records | Complete | Accepted | | 7 | Correction Register | Corrections and status | 28 corrections recorded | Accepted | | 8 | Software Requirements Specification | Approved BRN WMS SRS | Complete | Accepted | | 9 | Software Design | Approved BRN WMS design | Approved V1.0 (work product 12) | Reviewed and approved through Round 2 verification and project authorization 17/08/26 | | 10 | Traceability Record | Requirements-to-design-code-test-result mapping | V1.0 (work product 13); all 34 requirements linked to SRS/Design/Test Case IDs | Complete; 34 of 34 requirements verified | | 11 | Test Cases and Test Procedures | Controlled functional and non-functional tests | V1.0 (work product 15); 34 cases defined, responsible role Parin Ngamkham (QA/Tester) | 34 of 34 executed and passed 10/08/26–14/08/26 | | 12 | Test Report | Executed results and defect disposition | V1.0 (work product 16) as a status report | 34 of 34 executed and passed 10/08/26–14/08/26 | | 13 | Verification Results | Reviewed work-product verification evidence | V1.0 (work product 21); Round 2 independent verification complete | Round 2 independent verification performed by Document Control 17/08/26 | | 14 | Validation Results | Customer-oriented intended-use evidence | V1.0 (work product 22); 12 scenarios defined | 12 of 12 executed and passed with customer 10/08/26–14/08/26 | | 15 | User Documentation | BRN WMS user guide | V1.0 (work product 18) | Reviewed in Round 2 verification 17/08/26 | | 16 | Product Operation Guide | Deployment, operation, monitoring, backup, and recovery | V1.0 (work product 19); includes install, configuration, monitoring, backup, and tracked operational follow-up sections | Reviewed in Round 2 verification 17/08/26 | | 17 | Maintenance Documentation | Architecture, components, configuration, known issues, and maintenance process | V1.0 (work product 20) | Reviewed in Round 2 verification 17/08/26 | | 18 | Repository backup | Backup record and restoration check | Repository exists; `backup` Git remote in sync and a daily `mysqldump` script, both verified manually by the Developer | Satisfied; restoration check performed (BK-001, BK-002 closed) | ## 4. Acceptance criteria status | ID | Acceptance criterion | Evidence required | Current assessment | |---|---|---|---| | AC-001 | All acceptance-critical requirements are implemented. | Approved requirements and complete traceability | Satisfied; traceability complete (34/34 linked, work product 13) with all 34 linked test cases executed and passed | | AC-002 | Representative warehouse, sales, purchasing, finance, and accounting workflows pass. | Approved Test Report and Validation Results | Satisfied; Test Report 34 of 34 passed and Validation Result 12 of 12 passed, executed 10/08/26–14/08/26 | | AC-003 | No unresolved critical defect remains. | Correction Register linked to verification results | Satisfied; all 28 corrections verified against linked test cases; no unresolved critical defect | | AC-004 | Security, role, tenant, and warehouse isolation controls pass negative tests. | Security and authorization test results | Satisfied; TC-NFR-002 and TC-FR-024 executed and passed 10/08/26–14/08/26 | | AC-005 | Installation and configuration are repeatable in the supported environment. | Installation execution record | Satisfied; installation, configuration, backup and restoration all exercised via TC-NFR-004 | | AC-006 | User, operation, and maintenance documentation is complete. | Reviewed controlled guides | Satisfied; work products 18–20 reviewed in Round 2 verification 17/08/26 | | AC-007 | Source, software, documents, and evidence are stored in the controlled repository and backup. | Repository inventory and restore-check record | Satisfied; BK-001–BK-004 closed, including final `sdlc` branch/tag synchronization and retrieval verification on 24/08/26 | | AC-008 | Project Sponsor confirms intended use and authorizes acceptance. | Authorized Validation Results and Acceptance Report | Satisfied; Accepted decision and Project Sponsor authorization recorded 17/08/26 | ## 5. Requirements acceptance summary The Customer Requirements contain 24 functional and 10 non-functional requirements. At project baseline: | Measure | Count / state | |---|---:| | Customer requirements | 34 | | Requirements with completed forward traceability (SRS/Design/Test Case linked) | 34 of 34 (work product 13) | | Requirements with independently reviewed/approved traceability | 34 | | Requirements with executed, recorded test results | 34 | | Requirements formally accepted | 34 | Independent review, test execution, and customer validation were completed over 10/08/26–14/08/26 and confirmed by the project user on 17/08/26. Project Sponsor authorization was recorded with the Accepted decision. ## 6. Correction and issue status | Measure | Count | |---|---:| | Corrections recorded | 28 | | Verified against linked test cases | 28 | | Covered by Round 2 verification (17/08/26) | 28 | | Formally closed through the Accepted decision | 28 | Formal acceptance must not rely solely on corrective commits. Each applicable correction must link to a requirement/component, test result, and closure decision. ## 7. Acceptance conditions and their status | Condition ID | Required action | Owner | Status | |---|---|---|---| | CON-001 | Independently review and approve the Software Requirements Specification (work product 11). | Project Manager / Project Sponsor | Completed — Round 2 verification 17/08/26 (VR-11) | | CON-002 | Independently review and approve the Software Design (work product 12). | Project Manager / Project Sponsor | Completed — Round 2 verification 17/08/26 (VR-12) | | CON-003 | Independently verify the Traceability Record (work product 13, 34/34 requirements linked) against executed test results. | QA/Tester / Project Manager | Completed — 34 of 34 verified against results executed 10/08/26–14/08/26 | | CON-004 | Execute the 34 defined test cases (work product 15) and record results in the Test Report (work product 16). | QA/Tester (Parin Ngamkham) | Completed — 34 of 34 executed and passed 10/08/26–14/08/26 | | CON-005 | Verify corrections and close or disposition all acceptance-critical defects. | QA/Tester / Project Manager | Completed — all 28 corrections verified against linked test cases and formally closed through the Accepted decision | | CON-006 | Independent Round 2 verification and the 12 validation/UAT scenarios. | Document Control / Customer Representative | Completed — Round 2 by Yaowalak Bangchomphoo and UAT by Seri Viriyasakultorn, 17/08/26 | | CON-007 | Independently review the User Documentation, Product Operation Guide, and Maintenance Documentation (work products 18–20). | Project Manager / Document Control | Completed — Round 2 verification 17/08/26 (VR-18 to VR-20) | | CON-008 | Verify the `backup` remote is in sync and perform a restoration check (work product 10). | Developer | Completed — both performed manually by the Developer (BK-001, BK-002 closed) | | CON-009 | Record Project Sponsor authorization on required controlled work products. | Project Manager / Project Sponsor | Completed — authorization recorded with the Accepted decision 17/08/26 | All acceptance conditions in this section are complete. Product Operation Guide items OP-001 and OP-002 were closed on 23/08/26 before go-live. Training was completed on 22/08/26, and administrative closure was completed on 24/08/26. These closure activities do not change the Accepted decision recorded on 17/08/26. ## 8. Recommended decision **Recommended decision at 17/08/26: Accepted.** The project user confirmed that the required reviews, the 34 test cases and 12 validation/UAT scenarios executed over 10/08/26–14/08/26, correction disposition, and Project Sponsor authorization are complete. This supports the recorded Accepted decision. ## 9. Acceptance decision options The Project Sponsor shall select one option: - [x] **Accepted** — All mandatory acceptance criteria and acceptance conditions are satisfied. - [ ] **Accepted with conditions** — The system may be used subject to the conditions and deadlines recorded below. - [ ] **Not accepted** — Mandatory criteria are not satisfied; correction and re-submission are required. - [ ] **Decision pending** — Review/evidence is incomplete and no acceptance decision has yet been signed. Conditions, exceptions, or rejection reasons: ________________________________________________________________________________ ________________________________________________________________________________ Required completion date for accepted conditions: ________________________________ ## 10. Delivery and acceptance authorization ### Delivered by Name: Apirach Supattaratpateep Role: Project Manager Signature: ______________________________________________ Date: ___________________________________________________ ### Technical delivery confirmed by Name: Thanakorn Sathitwitayakul Role: Developer Signature: ______________________________________________ Date: ___________________________________________________ ### Received and decided by Name: Seri Viriyasakultorn Project roles: Project Sponsor / Customer Representative / Authorized Approver Position: Managing Director Company: B.R.N. Enterprise Co., Ltd. Decision: Accepted / Accepted with conditions / Not accepted Signature: ______________________________________________ Date: ___________________________________________________