# Verification Results | Document field | Value | |---|---| | Document | Verification Results | | Project | BRN WMS | | Project code | 200-WMS-26-001-00 | | Title | Record of Verification Against Standard Requirements | | Project period | 05/01/26–24/08/26 | | Release | 17/08/26 V1.0 | | Standard | ISO/IEC 29110 Basic Profile | | Review round | Round 2 completed 17/08/26 — independent verification performed by Yaowalak Bangchomphoo, Document Control | | Organizer | Apirach Supattaratpateep (Project Manager), Noppong Chareunsook (System Analyst), Thanakorn Sathitwitayakul (Developer) | | Round 2 verifier | Yaowalak Bangchomphoo — Document Control, independent of the document preparer | | Status | Final — Round 2 independent verification complete | ## Objective Confirm the correctness and completeness of the SDLC work products delivered so far, against ISO/IEC 29110 Basic Profile document-control expectations, before they are treated as ready for Project Sponsor review. ## 1. Deliverables under review PM work products 1–10 and SI work products 11–20 (this and work product 22 are excluded, being the verification/validation records themselves). ## 2. Verification items Each row checks the document-control header, content, project coverage, and approval block. | ID | Work product | Header complete | Purpose met | Evidence basis disclosed | Approval block present | Result | |---|---|---|---|---|---|---| | VR-01 | Statement of Work | Yes | Yes | N/A | Yes | Passed | | VR-02 | Project Plan (Work Schedule, SPP, Customer Requirements) | Yes | Yes | Yes, where applicable | Yes | Passed | | VR-03 | Progress Status Records (13) | Yes | Yes | Yes | Yes | Passed | | VR-04 | Correction Register | Yes | Yes | Yes | Yes | Passed | | VR-05 | Acceptance Report | Yes | Yes | Yes | Yes | Passed | | VR-06 | Change Report (CH-001–CH-003) | Yes | Yes | Yes | Yes | Passed | | VR-07 | Meeting Record (MTG-001–MTG-004) | Yes | Yes | Yes — each record discloses its evidence basis and marks unrecorded fields | Yes | Passed | | VR-08 | Software Configuration | Yes | Yes | Yes | Yes | Passed | | VR-09 | Project Repository | Yes | Yes | Yes | Yes | Passed | | VR-10 | Project Repository (Backup) | Yes | Yes | Yes — backup sync and restoration verified manually by the Developer | Yes | Passed | | VR-11 | Software Requirements Specification | Yes | Yes | Yes — scaling note explains granularity choice | Yes | Passed | | VR-12 | Software Design | Yes | Yes | Yes | Yes | Passed | | VR-13 | Traceability Record | Yes | Yes | Yes | Yes | Passed | | VR-14 | Software Components | Yes | Yes | Yes | Yes | Passed | | VR-15 | Test Cases and Test Procedures | Yes | Yes | Yes — all 34 cases executed and passed 10/08/26–14/08/26 | Yes | Passed | | VR-16 | Test Report | Yes | Yes | Yes — records 34 of 34 executed and passed 10/08/26–14/08/26 | Yes | Passed | | VR-17 | Software | Yes | Yes | Yes | Yes | Passed | | VR-18 | Software User Documentation | Yes | Yes | N/A (forward-facing usage guide) | Yes | Passed | | VR-19 | Product Operation Guide | Yes | Yes | Yes | Yes | Passed | | VR-20 | Maintenance Documentation | Yes | Yes | Yes | Yes | Passed | ## 3. Risk and constraint note 1. Round 1 was a self-review by the document preparer (the Developer). Round 2 was performed on 17/08/26 by Yaowalak Bangchomphoo, Document Control, who is independent of the Developer and whose assigned role covers identifiers, versions, approvals, distribution, repository content, and evidence — the same attributes the verification items in Section 2 check. Per-item reviewer notes were not retained beyond the pass/fail results recorded above. 2. Test execution, verification, and validation facilitation (work products 15, 16, 22) are now assigned to Parin Ngamkham, QA / Tester, independent of the Developer who prepared this record. This mitigates the self-testing concern for those three work products specifically. Round 1 of this record and of work products 1–14 and 17–21 was a self-review by the Developer who authored them; that self-review was superseded by the Round 2 independent verification performed by Document Control on 17/08/26. 3. All 34 functional/non-functional test cases and all 12 UAT/validation scenarios were executed over 10/08/26–14/08/26 and passed. 4. Future reviews should retain per-item reviewer notes alongside the pass/fail result, so the basis of each verification decision is auditable and not only its outcome. ## 4. Recommendation Capture the Round 2 verifier's signature on this record, and retain per-item review notes in future projects. ## 5. Approval ### Prepared by (Round 2 independent verification) Name: Yaowalak Bangchomphoo Role: Document Control Signature: ______________________________________________ Date: ___________________________________________________ ### Reviewed by Name: Apirach Supattaratpateep Role: Project Manager Signature: ______________________________________________ Date: ___________________________________________________ ### Reviewed and authorized by Name: Seri Viriyasakultorn Project roles: Project Sponsor / Customer Representative / Authorized Approver Position: Managing Director Company: B.R.N. Enterprise Co., Ltd. Signature: ______________________________________________ Date: ___________________________________________________