# Meeting Record — Completion Boundary Checkpoint
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Meeting Record |
|
||||
| Checkpoint ID | MTG-004 |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Phase | Project Closure (reconstructed) |
|
||||
| Task ID / Task Name | Not recorded — no contemporaneous task breakdown exists for this date |
|
||||
| Meeting date (Git evidence) | 14/08/26 |
|
||||
| Time | Not recorded |
|
||||
| Location | Not recorded |
|
||||
| Organizer | Not recorded |
|
||||
| Recorder | Not recorded |
|
||||
| CC | Not recorded |
|
||||
| Release | 14/08/26 V1.0 |
|
||||
| Status | Final — reconstructed checkpoint; no meeting is asserted to have occurred |
|
||||
|
||||
## Disclosure
|
||||
|
||||
No contemporaneous meeting minutes exist for this date. This record documents a Git-evidenced milestone checkpoint only. No attendee, agenda, or discussion content is fabricated; fields below are marked "Not recorded" where no evidence exists.
|
||||
|
||||
**Git evidence:** `dd48a8b` — Demo Data Population
|
||||
|
||||
## Participants
|
||||
|
||||
Not recorded — no attendance evidence exists. The three confirmed standing project roles (Project Sponsor, Project Manager, Developer / System Analyst) are listed in `SDLC_DOCS.md`; their presence at any specific meeting on this date is not evidenced.
|
||||
|
||||
## Project progress
|
||||
|
||||
| หมวดงาน | สถานะ | ความคืบหน้า (%) | รายละเอียด |
|
||||
|---|---|---:|---|
|
||||
| Project Closure | Reconstructed checkpoint | N/A — no contemporaneous plan baseline to measure against | Activity on the agreed project-completion boundary date (05/01/26–14/08/26); treated as the completion checkpoint. |
|
||||
|
||||
## Agenda
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Discussion summary
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Action items
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Next meeting
|
||||
|
||||
Not recorded — no contemporaneous evidence. From the release date of this record forward, meetings held for BRN WMS should use a fully populated Minutes of Meeting record (agenda, attendance, discussion, and action items captured contemporaneously) rather than a reconstructed checkpoint.
|
||||
|
||||
## Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: คุณอภิรัชต์ สุภัทรประทีป
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: ธนกร สถิตวิทยากุล
|
||||
Role: Developer / System Analyst
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: คุณเสรี วิริยะสกุลธรณ์
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: กรรมการผู้จัดการ
|
||||
Company: บริษัท บี.อาร์.เอ็น. เอ็นเตอร์ไพรส์ จำกัด
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
-75
@@ -1,75 +0,0 @@
|
||||
# Meeting Record — Development Substantially Complete Checkpoint
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Meeting Record |
|
||||
| Checkpoint ID | MTG-002 |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Phase | Development (reconstructed) |
|
||||
| Task ID / Task Name | Not recorded — no contemporaneous task breakdown exists for this date |
|
||||
| Meeting date (Git evidence) | 29/05/26 |
|
||||
| Time | Not recorded |
|
||||
| Location | Not recorded |
|
||||
| Organizer | Not recorded |
|
||||
| Recorder | Not recorded |
|
||||
| CC | Not recorded |
|
||||
| Release | 29/05/26 V1.0 |
|
||||
| Status | Final — reconstructed checkpoint; no meeting is asserted to have occurred |
|
||||
|
||||
## Disclosure
|
||||
|
||||
No contemporaneous meeting minutes exist for this date. This record documents a Git-evidenced milestone checkpoint only. No attendee, agenda, or discussion content is fabricated; fields below are marked "Not recorded" where no evidence exists.
|
||||
|
||||
**Git evidence:** `a0677d6` — Classe methods: remove reducdancy (last commit before the 03/08/26 stabilization commit)
|
||||
|
||||
## Participants
|
||||
|
||||
Not recorded — no attendance evidence exists. The three confirmed standing project roles (Project Sponsor, Project Manager, Developer / System Analyst) are listed in `SDLC_DOCS.md`; their presence at any specific meeting on this date is not evidenced.
|
||||
|
||||
## Project progress
|
||||
|
||||
| หมวดงาน | สถานะ | ความคืบหน้า (%) | รายละเอียด |
|
||||
|---|---|---:|---|
|
||||
| Development | Reconstructed checkpoint | N/A — no contemporaneous plan baseline to measure against | Last commit before the project period's development phase gives way to stabilization; treated as the development-complete checkpoint. |
|
||||
|
||||
## Agenda
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Discussion summary
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Action items
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Next meeting
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: คุณอภิรัชต์ สุภัทรประทีป
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: ธนกร สถิตวิทยากุล
|
||||
Role: Developer / System Analyst
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: คุณเสรี วิริยะสกุลธรณ์
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: กรรมการผู้จัดการ
|
||||
Company: บริษัท บี.อาร์.เอ็น. เอ็นเตอร์ไพรส์ จำกัด
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
-75
@@ -1,75 +0,0 @@
|
||||
# Meeting Record — Project Initiation Checkpoint
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Meeting Record |
|
||||
| Checkpoint ID | MTG-001 |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Phase | Project Initiation (reconstructed) |
|
||||
| Task ID / Task Name | Not recorded — no contemporaneous task breakdown exists for this date |
|
||||
| Meeting date (Git evidence) | 19/02/26 |
|
||||
| Time | Not recorded |
|
||||
| Location | Not recorded |
|
||||
| Organizer | Not recorded |
|
||||
| Recorder | Not recorded |
|
||||
| CC | Not recorded |
|
||||
| Release | 19/02/26 V1.0 |
|
||||
| Status | Final — reconstructed checkpoint; no meeting is asserted to have occurred |
|
||||
|
||||
## Disclosure
|
||||
|
||||
No contemporaneous meeting minutes exist for this date. This record documents a Git-evidenced milestone checkpoint only. No attendee, agenda, or discussion content is fabricated; fields below are marked "Not recorded" where no evidence exists.
|
||||
|
||||
**Git evidence:** `9a50080` — init wms
|
||||
|
||||
## Participants
|
||||
|
||||
Not recorded — no attendance evidence exists. The three confirmed standing project roles (Project Sponsor, Project Manager, Developer / System Analyst) are listed in `SDLC_DOCS.md`; their presence at any specific meeting on this date is not evidenced.
|
||||
|
||||
## Project progress
|
||||
|
||||
| หมวดงาน | สถานะ | ความคืบหน้า (%) | รายละเอียด |
|
||||
|---|---|---:|---|
|
||||
| Project Initiation | Reconstructed checkpoint | N/A — no contemporaneous plan baseline to measure against | First implementation commit in the repository, treated as the initiation checkpoint. |
|
||||
|
||||
## Agenda
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Discussion summary
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Action items
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Next meeting
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: คุณอภิรัชต์ สุภัทรประทีป
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: ธนกร สถิตวิทยากุล
|
||||
Role: Developer / System Analyst
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: คุณเสรี วิริยะสกุลธรณ์
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: กรรมการผู้จัดการ
|
||||
Company: บริษัท บี.อาร์.เอ็น. เอ็นเตอร์ไพรส์ จำกัด
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
-75
@@ -1,75 +0,0 @@
|
||||
# Meeting Record — Stabilization Checkpoint
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Meeting Record |
|
||||
| Checkpoint ID | MTG-003 |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Phase | Stabilization (reconstructed) |
|
||||
| Task ID / Task Name | Not recorded — no contemporaneous task breakdown exists for this date |
|
||||
| Meeting date (Git evidence) | 03/08/26 |
|
||||
| Time | Not recorded |
|
||||
| Location | Not recorded |
|
||||
| Organizer | Not recorded |
|
||||
| Recorder | Not recorded |
|
||||
| CC | Not recorded |
|
||||
| Release | 03/08/26 V1.0 |
|
||||
| Status | Final — reconstructed checkpoint; no meeting is asserted to have occurred |
|
||||
|
||||
## Disclosure
|
||||
|
||||
No contemporaneous meeting minutes exist for this date. This record documents a Git-evidenced milestone checkpoint only. No attendee, agenda, or discussion content is fabricated; fields below are marked "Not recorded" where no evidence exists.
|
||||
|
||||
**Git evidence:** `b2c4374` — fix login and configurations
|
||||
|
||||
## Participants
|
||||
|
||||
Not recorded — no attendance evidence exists. The three confirmed standing project roles (Project Sponsor, Project Manager, Developer / System Analyst) are listed in `SDLC_DOCS.md`; their presence at any specific meeting on this date is not evidenced.
|
||||
|
||||
## Project progress
|
||||
|
||||
| หมวดงาน | สถานะ | ความคืบหน้า (%) | รายละเอียด |
|
||||
|---|---|---:|---|
|
||||
| Stabilization | Reconstructed checkpoint | N/A — no contemporaneous plan baseline to measure against | Login/configuration correction after a gap since the 29/05/26 development checkpoint; treated as the stabilization checkpoint. |
|
||||
|
||||
## Agenda
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Discussion summary
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Action items
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Next meeting
|
||||
|
||||
Not recorded — no contemporaneous evidence.
|
||||
|
||||
## Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: คุณอภิรัชต์ สุภัทรประทีป
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: ธนกร สถิตวิทยากุล
|
||||
Role: Developer / System Analyst
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: คุณเสรี วิริยะสกุลธรณ์
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: กรรมการผู้จัดการ
|
||||
Company: บริษัท บี.อาร์.เอ็น. เอ็นเตอร์ไพรส์ จำกัด
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||