docs(sdlc): align V1.0 audit evidence

This commit is contained in:
Thanakorn
2026-08-19 14:11:00 +07:00
parent bbc3654180
commit 7d211be7e5
14 changed files with 78 additions and 75 deletions
@@ -7,20 +7,19 @@
| Project code | 200-WMS-26-001-00 |
| Title | Warehouse Management System Development Project Plan |
| Project period | 05/01/26–24/08/26 |
| Release | 17/08/26 V1.1 Final |
| Original baseline | 05/01/26 V1.0 Final |
| Release | 17/08/26 V1.0 Final |
| Planning baseline | 05/01/26 |
| Standard | ISO/IEC 29110 Basic Profile |
| Project Manager | Apirach Supattaratpateep |
| Status | Final — ready for review and authorized approval |
| Status | Final — reviewed and authorized |
## Revision history
| Version | Date | Change | Prepared by |
|---|---|---|---|
| V1.0 | 05/01/26 | Initial project plan issued at project start: scope, lifecycle, organization, resources, risks, quality, configuration and closure approach. | Apirach Supattaratpateep |
| V1.1 | 17/08/26 | Re-issued at closure. Section 6 records the lifecycle actually followed and the implementation commit count; Section 8.5 records the equipment-evidence position; Section 12.2 records achieved quality results; Section 16 records the naming/version conventions and repository state as applied across the controlled file set. Scope, organization and risk content from V1.0 are unchanged. | Apirach Supattaratpateep |
| V1.0 | 17/08/26 | Initial controlled issue. Consolidates the 05/01/26 planning baseline with lifecycle, quality, equipment-evidence, and configuration outcomes recorded through closure preparation. | Apirach Supattaratpateep |
Sections 6, 8.5, 12.2 and 16 describe outcomes as at 17/08/26; the remaining sections are the V1.0 baseline.
Sections 6, 8.5, 12.2 and 16 describe outcomes as at 17/08/26; the remaining sections retain the 05/01/26 planning baseline.
## 1. Purpose
@@ -348,7 +347,7 @@ BRN WMS document filenames do not append author initials.
### 16.2 Version declaration
Documents created for BRN WMS are released directly at `V1.0` once content is complete, without the example's separate `0.1`/`0.2` Draft stages — BRN WMS work products are not labeled `Draft` unless explicitly requested, per the same recorded decision. "Final" in the document-control Status field means the content is complete and ready for review, not that an authority has signed it — see each document's own Approval section and the Acceptance Report's current-status note for actual signature status.
Documents created for BRN WMS are released directly at `V1.0` once content is complete, without the example's separate `0.1`/`0.2` Draft stages — BRN WMS work products are not labeled `Draft` unless explicitly requested, per the same recorded decision. "Final" in the document-control Status field means the controlled content is complete; authorization and the project-acceptance decision are recorded in each document's Approval section and the Acceptance Report.
### 16.3 Repository and backup
@@ -356,7 +355,7 @@ Documents created for BRN WMS are released directly at `V1.0` once content is co
- Documents identify title, date, version, status, preparer, reviewer, and approver as applicable.
- Drafts remain distinguishable from approved baselines.
- The Project Repository contains the current controlled work products and supporting evidence (work product 9).
- The repository backup is maintained separately and checked during project closure (work product 10); that check was performed manually by the Developer (BK-001, BK-002 closed).
- The repository backup is maintained separately and checked during project closure (work product 10); the baseline and restoration checks were performed manually by the Developer (BK-001 and BK-002 closed), package completeness is recorded by BK-003, and final SDLC delivery-branch synchronization is tracked by BK-004 through 24/08/26.
- Superseded records are retained or archived according to organizational control practices.
## 17. Acceptance and closure