docs(sdlc): close training and operational actions
This commit is contained in:
+3
-3
@@ -16,9 +16,9 @@
|
||||
|
||||
| Version | Date | Change | Prepared by |
|
||||
|---|---|---|---|
|
||||
| V1.0 | 17/08/26 | Initial controlled issue. Records the 05/01/26 schedule baseline and actual outcomes through product acceptance; administrative handover and training continue through project closure on 24/08/26. | Apirach Supattaratpateep |
|
||||
| V1.0 | 17/08/26 | Initial controlled issue, subsequently updated with closure outcomes through 24/08/26: training, operational controls, delivery packaging, and repository-backup synchronization completed. | Apirach Supattaratpateep |
|
||||
|
||||
The Status, Actual/evidence date and Remarks columns below record outcomes as at 17/08/26. The Start, Finish and Duration columns retain the 05/01/26 planned baseline; where a task finished after its planned Finish date, the Remarks column states the actual finish.
|
||||
The Status, Actual/evidence date and Remarks columns below record outcomes through formal closure on 24/08/26. The Start, Finish and Duration columns retain the 05/01/26 planned baseline; where a task finished after its planned Finish date, the Remarks column states the actual finish.
|
||||
|
||||
## Schedule basis
|
||||
|
||||
@@ -48,7 +48,7 @@ The Status, Actual/evidence date and Remarks columns below record outcomes as at
|
||||
| 4.6 | Stabilization | Configuration and login corrections | Correct login and environment configuration issues identified after baseline. | Developer | 03/08/26 | 03/08/26 | 1 day | Configuration and login correction | Completed |
|
||||
| 4.7 | Stabilization | Prepare demonstration data | Populate controlled demonstration data for validation and handover support. | Developer / Tester | 14/08/26 | 14/08/26 | 1 day | Demonstration data | Completed |
|
||||
| 5.1 | Closure | Final repository and work-product review | Confirm required work products, traceability, configuration items, and unresolved actions. | Project Manager / Document Control | 10/08/26 | 24/08/26 | 15 days | Repository review and List of Evidence | Completed | Round 2 independent verification performed by Document Control on 17/08/26 |
|
||||
| 5.2 | Closure | Acceptance and project closure | Obtain authorized acceptance and record project closure and follow-up actions. | Project Sponsor / Project Manager | 14/08/26 | 24/08/26 | 11 days | Acceptance Report and closure record | In progress | Product acceptance and authorization completed 17/08/26; administrative handover and training continue through 24/08/26 |
|
||||
| 5.2 | Closure | Acceptance and project closure | Obtain authorized acceptance and record project closure and follow-up actions. | Project Sponsor / Project Manager | 14/08/26 | 24/08/26 | 11 days | Acceptance Report, Training Report, operational-control closure, and repository-backup record | Completed | Product accepted 17/08/26; training completed 22/08/26; operational controls closed 23/08/26; administrative and repository-backup closure completed 24/08/26 |
|
||||
|
||||
## Milestones
|
||||
|
||||
|
||||
Reference in New Issue
Block a user