# Progress Status Record 1 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 05/01/26–23/01/26 |
|
||||
| Report date | 23/01/26 |
|
||||
| Release | 23/01/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Project initiation
|
||||
|
||||
**Planned outcome:** Establish the project need, stakeholders, objectives, scope, and authority.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Formal project start and scope boundary were established from the agreed lifecycle.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 1.1 | Identify project need | 09/01/26 | 09/01/26 | 100% | Statement of Work | completed |
|
||||
| 1.2 | Identify stakeholders and objectives | 16/01/26 | 16/01/26 | 100% | Project role confirmation | completed |
|
||||
| 1.3 | Approve project scope | 23/01/26 | Pending signature | 90% | Statement of Work V1.0 Final | Approval pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Agreed |
|
||||
| Evidence reference | Statement of Work; Work Schedule |
|
||||
| Overall period status | Not rated — no contemporaneous rating was recorded for this period |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Initiation tasks 1.1 and 1.2 finished on their planned dates. Task 1.3 (scope approval) is complete in content but awaits authorized signature.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Maintain project initiation records and approvals.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete customer requirements and project planning baseline.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+79
@@ -0,0 +1,79 @@
|
||||
# Progress Status Record 2 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 12/01/26–18/02/26 |
|
||||
| Report date | 18/02/26 |
|
||||
| Release | 18/02/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Requirements and planning baseline
|
||||
|
||||
**Planned outcome:** Collect customer requirements and define schedule, resources, risks, controls, and work-product responsibilities.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Customer Requirements, Work Schedule, and Software Project Plan were prepared from the agreed scope and the available implementation evidence.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 2.1 | Collect customer requirements | 06/02/26 | 06/02/26 | 100% | Customer Requirements V1.0 Final | completed |
|
||||
| 2.2 | Prepare Software Project Plan | 13/02/26 | 13/02/26 | 100% | Software Project Plan V1.0 Final | completed |
|
||||
| 2.3 | Baseline requirements and schedule | 18/02/26 | 18/02/26 | 100% | Work Schedule and Project Plan | completed; approval pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Document |
|
||||
| Evidence reference | Project Plan work products |
|
||||
| Overall period status | Not rated — no contemporaneous rating was recorded for this period |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Planning tasks 2.1–2.3 all finished on their planned dates. The requirements and schedule baseline is set for development to begin 19/02/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Exact elicitation dates and approvals are unavailable.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Begin controlled software implementation on 19/02/26.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+76
@@ -0,0 +1,76 @@
|
||||
# Progress Status Record 3 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 19/02/26–25/02/26 |
|
||||
| Report date | 25/02/26 |
|
||||
| Release | 25/02/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Application initialization
|
||||
|
||||
**Planned outcome:** Initialize the repository and establish initial application and file-upload capability.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** WMS repository initialized; verification commit and dropzone/file-upload work completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.1 | Initialize WMS application | 25/02/26 | 25/02/26 | 100% | Git `9a50080`–`1843308` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `9a50080`, `42a3876`, `8625652`, `1843308` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.1 finished on its planned date of 25/02/26. No schedule deviation in this period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** No unresolved blocker is evidenced in the repository for this period.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Protect configuration, address security findings, and establish the stock database foundation.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+76
@@ -0,0 +1,76 @@
|
||||
# Progress Status Record 4 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 09/03/26–17/03/26 |
|
||||
| Report date | 17/03/26 |
|
||||
| Release | 17/03/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Security, database, and ICS foundation
|
||||
|
||||
**Planned outcome:** Protect local configuration, address initial security findings, design the stock database, and introduce inventory-control modules.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Configuration was removed from tracking, security-audit fixes were applied, stock database design was committed, and ICS modules were introduced.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.2 | Security and database foundation | 17/03/26 | 17/03/26 | 100% | Git `93d903c`–`a4f474b` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `93d903c`, `7cb78d0`, `2e558a5`, `a4f474b` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.2 finished on its planned date of 17/03/26. No schedule deviation, though commit activity was concentrated at the start and end of the period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** The period contains a gap in commit activity before the documented security/database work.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Develop stock visibility, warehouse structure, product controls, and operational reports.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+76
@@ -0,0 +1,76 @@
|
||||
# Progress Status Record 5 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 09/04/26–29/04/26 |
|
||||
| Report date | 29/04/26 |
|
||||
| Release | 29/04/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Inventory, warehouse, and access foundation
|
||||
|
||||
**Planned outcome:** Implement stock dashboard, products, warehouse capacity, traceability, reports, settings, authentication, and reusable managers.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Dashboard, product files, OOP utilities, capacity/occupancy, lot/serial/expiry, reports, settings, login/onboarding, and manager classes were implemented.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.3 | Inventory and warehouse modules | 29/04/26 | 29/04/26 | 100% | Git `3b8f94f`–`db5c47b` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `3b8f94f` through `db5c47b` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.3 finished on its planned date of 29/04/26. No schedule deviation in this period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Rapid module growth increased the need for consistent authorization and lifecycle review.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete document approval logic, orders, warehouse layers, barcode, and role guards.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+77
@@ -0,0 +1,77 @@
|
||||
# Progress Status Record 6 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 30/04/26–08/05/26 |
|
||||
| Report date | 08/05/26 |
|
||||
| Release | 08/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Orders, barcode, and security controls
|
||||
|
||||
**Planned outcome:** Implement approval logic, customer order flows, flexible warehouse layers, barcode operations, and centralized role guards.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Password scoring, stock approval, orders/returns/invoices, switchable warehouse layers, barcode functions, role guards, security fixes, and naming/session corrections were completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.4 | Authentication and onboarding | 12/05/26 | In progress at 08-May | 70% | Commits through 08/05/26 | In progress; carried forward |
|
||||
| 3.5 | Order and barcode workflows | 08/05/26 | 08/05/26 | 100% | 02/05/26–08/05/26 commits | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 30/04/26–08/05/26 commits |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.5 finished on its planned date of 08/05/26. Task 3.4 is running to its planned finish of 12/05/26 and is carried forward at 70%.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Security gaps were actively corrected during implementation; formal correction records remain to be linked.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Prepare production setup and introduce accounting capabilities.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+78
@@ -0,0 +1,78 @@
|
||||
# Progress Status Record 7 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 11/05/26–13/05/26 |
|
||||
| Report date | 13/05/26 |
|
||||
| Release | 13/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Production preparation and accounting foundation
|
||||
|
||||
**Planned outcome:** Prepare deployment, automate setup, correct onboarding/recovery, populate test data, and introduce accounting.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Production preparation, dynamic base URL, automated setup, password recovery, onboarding fixes, test data, dashboard updates, and accounting modules were committed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.4 | Authentication and onboarding | 12/05/26 | 12/05/26 | 100% | Login/onboarding and recovery commits | Completed |
|
||||
| 3.6 | Production preparation and setup | 13/05/26 | 13/05/26 | 100% | 11/05/26–13/05/26 commits | Completed |
|
||||
| 3.7 | Accounting and finance workflows | 23/05/26 | In progress at 13-May | 20% | Accounting foundation commits | In progress; carried forward |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 11/05/26–13/05/26 commits |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Tasks 3.4 and 3.6 finished on their planned dates. Task 3.7 is running to its planned finish of 23/05/26 and is carried forward at 20%.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Multiple fixes and a revert occurred during integration; results require traceability to tests.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Integrate accounting workflows, document control, access limits, and supporting services.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+78
@@ -0,0 +1,78 @@
|
||||
# Progress Status Record 8 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 20/05/26–23/05/26 |
|
||||
| Report date | 23/05/26 |
|
||||
| Release | 23/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Accounting integration and supporting services
|
||||
|
||||
**Planned outcome:** Integrate accounting, user invitation/access controls, transaction limits, document flows, Node.js, aggregates, and reports.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Accounting workflows, access controls, setup script, soft delete, Socket service, GL aggregation, accounting reports, journal batching, and GL automation were implemented.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.7 | Accounting and finance workflows | 23/05/26 | 23/05/26 | 100% | 13/05/26–23/05/26 accounting commits | Completed |
|
||||
| 3.8 | Real-time services and scheduled jobs | 27/05/26 | In progress at 23-May | 45% | Node.js and GL aggregate commits | In progress; carried forward |
|
||||
| 3.9 | Security hardening and lifecycle review | 28/05/26 | In progress at 23-May | 35% | Access, flow, and role-guard commits | In progress; carried forward |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 20/05/26–23/05/26 commits |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.7 finished on its planned date of 23/05/26. Tasks 3.8 and 3.9 are running to their planned finishes of 27/05/26 and 28/05/26 and are carried forward.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Integration breadth increased regression and tenant-isolation risk.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete security hardening, notification control, sequencing, scheduler, tenant scoping, and final review.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+78
@@ -0,0 +1,78 @@
|
||||
# Progress Status Record 9 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 24/05/26–29/05/26 |
|
||||
| Report date | 29/05/26 |
|
||||
| Release | 29/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Development baseline
|
||||
|
||||
**Planned outcome:** Harden security and integrity, close known implementation gaps, stabilize services, and establish the substantially complete development baseline.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Session controls, aggregates, notifications, security/lifecycle reviews, transaction limits, document sequencing, role guards, scheduler fixes, bin naming, tenant scoping, and final refactoring were completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.8 | Real-time services and scheduled jobs | 27/05/26 | 27/05/26 | 100% | 22–27 May Node.js/scheduler commits | Completed |
|
||||
| 3.9 | Security hardening and lifecycle review | 28/05/26 | 28/05/26 | 100% | 21–28 May hardening/review commits | Completed |
|
||||
| 3.10 | Refactor and development baseline | 29/05/26 | 29/05/26 | 100% | Git `a0677d6` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 24/05/26–29/05/26 commits; final `a0677d6` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Tasks 3.8, 3.9 and 3.10 all finished on their planned dates. The development baseline is reached as scheduled on 29/05/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Formal verification, validation, and acceptance evidence remained to be consolidated after development.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Conduct verification, validation, documentation, and delivery preparation.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+79
@@ -0,0 +1,79 @@
|
||||
# Progress Status Record 10 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 30/05/26–31/07/26 |
|
||||
| Report date | 31/07/26 |
|
||||
| Release | 31/07/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Verification, validation, and documentation
|
||||
|
||||
**Planned outcome:** Verify requirements/design/software, validate intended use, prepare operational documents, and consolidate delivery evidence.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** This activity period covers assurance and documentation activities within the agreed timeline.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 4.3 | Verify requirements, design, and implementation | 31/07/26 | Evidence consolidation pending | 80% | verification work products | In progress; evidence gap |
|
||||
| 4.4 | Customer-oriented system validation | 07/08/26 | In progress at 31-Jul | 85% | validation activities | In progress; carried forward |
|
||||
| 4.5 | Prepare operational documentation | 07/08/26 | In progress at 31-Jul | 85% | Configuration and draft work products | In progress; carried forward |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Document |
|
||||
| Evidence reference | SRS, Design, Traceability, Test, Guide, Verification, and Validation work products |
|
||||
| Overall period status | Amber |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 4.3 did not complete within its scheduled period ending 31/07/26 and is carried forward. Tasks 4.4 and 4.5 are running to their planned finish of 07/08/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Missing evidence creates an audit and acceptance gap.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete stabilization corrections, finalize evidence, and obtain stakeholder review.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+76
@@ -0,0 +1,76 @@
|
||||
# Progress Status Record 11 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 03/08/26 |
|
||||
| Report date | 03/08/26 |
|
||||
| Release | 03/08/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Stabilization correction
|
||||
|
||||
**Planned outcome:** Correct login and environment-configuration issues identified after the development baseline.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Login and configuration corrections were committed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 4.6 | Configuration and login corrections | 03/08/26 | 03/08/26 | 100% | Git `b2c4374` | Completed; formal correction closure pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `b2c4374` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 4.6 finished on its planned date of 03/08/26. No schedule deviation in this period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** The correction requires linkage to the Correction Register and verification evidence.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Prepare representative demonstration data and complete final delivery checks.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+81
@@ -0,0 +1,81 @@
|
||||
# Progress Status Record 12 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 04/08/26–14/08/26 |
|
||||
| Report date | 14/08/26 |
|
||||
| Release | 14/08/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Demonstration data and closure preparation
|
||||
|
||||
**Planned outcome:** Prepare controlled demonstration data, execute the defined tests and validation scenarios, and complete final checks ahead of closure.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Demonstration data was committed on 14/08/26. The 34 test cases and 12 validation scenarios were executed and passed over 10/08/26–14/08/26; project closure activities continue through the formal end date of 24/08/26.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 4.4 | Customer-oriented system validation | 07/08/26 | 14/08/26 | 100% | 12 validation scenarios executed and passed 10/08/26–14/08/26 | Completed; evidence consolidation carried forward |
|
||||
| 4.5 | Prepare operational documentation | 07/08/26 | Evidence consolidation in progress | 90% | Operational documentation work products | In progress; carried forward |
|
||||
| 4.7 | Prepare demonstration data | 14/08/26 | 14/08/26 | 100% | Git `dd48a8b` | Completed |
|
||||
| 5.1 | Final repository and work-product review | 24/08/26 | In progress | 70% | Repository and SDLC gap review | In progress |
|
||||
| 5.2 | Acceptance and project closure | 24/08/26 | Pending signature | 75% | Closure activities in progress | Acceptance pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Project milestone |
|
||||
| Evidence reference | `dd48a8b`; test and validation execution 10/08/26–14/08/26 |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 4.7 finished on its planned date of 14/08/26. Task 4.4 completed on 14/08/26, after its planned finish of 07/08/26; task 4.5 is carried forward. Tasks 5.1 and 5.2 run to the project end date of 24/08/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Test and validation execution is complete, but the results are not yet consolidated into the controlled work products, and formal signatures remain open.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Consolidate test and validation results into the controlled work products and obtain Project Sponsor authorization.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+80
@@ -0,0 +1,80 @@
|
||||
# Progress Status Record 13 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 15/08/26–17/08/26 |
|
||||
| Report date | 17/08/26 |
|
||||
| Release | 17/08/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Evidence consolidation and authorization preparation
|
||||
|
||||
**Planned outcome:** Complete missing controlled work products, align roles, and prepare records for review and authorization.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Test and validation results from the 10/08/26–14/08/26 execution window were consolidated and confirmed on 17/08/26, Round 2 independent verification was performed, and the remaining controlled work products were completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 5.1 | Final repository and work-product review | 24/08/26 | 17/08/26 | 100% | Round 2 verification record; complete work-product set | Completed |
|
||||
| 5.2 | Acceptance and project closure | 24/08/26 | 17/08/26 | 90% | Acceptance Report decision Accepted | Accepted; Sponsor signature capture outstanding |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Document |
|
||||
| Evidence reference | Current `sdlc/` repository and Git status |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
|
||||
Task 5.1 completed 17/08/26. Task 5.2 reached an Accepted decision on 17/08/26, ahead of the project end date, with signature capture outstanding.
|
||||
|
||||
**Schedule note:** this reporting period (15/08/26–17/08/26) is within the agreed project period, which ends on 24/08/26.
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Verification, validation, and acceptance are complete. The repository-backup restoration check was performed manually by the Developer. One item remains open: Project Sponsor signature capture (CON-009).
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Obtain Project Sponsor signatures on the controlled work products.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||