# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690109 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 1 : 9 มกราคม 2569 |
|
||||
| Reporting Period | 5 มกราคม 2569 – 9 มกราคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 1.1 | Kick-off Meeting | 5–9 ม.ค. 69 | ApS, SeV | Completed | 100 | เปิดโครงการอย่างเป็นทางการ ชี้แจงขอบเขตและทีมงานครบทุกบทบาท |
|
||||
| 1.2 | Identify Stakeholders | 12–16 ม.ค. 69 | ApS, YaB | In Progress | 40 | อยู่ระหว่างรวบรวมรายชื่อผู้มีส่วนได้ส่วนเสียและระดับการมีส่วนร่วม |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 2 | 16 มกราคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ทบทวนรายชื่อผู้มีส่วนได้ส่วนเสียและเริ่มกำหนดวัตถุประสงค์โครงการ |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
+56
@@ -0,0 +1,56 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690123 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 2 : 23 มกราคม 2569 |
|
||||
| Reporting Period | 12 มกราคม 2569 – 23 มกราคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 1.2 | Identify Stakeholders | 12–16 ม.ค. 69 | ApS, YaB | Completed | 100 | จัดทำ Stakeholder Register ครบ 6 บทบาทหลักและผู้ใช้งานที่เกี่ยวข้อง |
|
||||
| 1.3 | Define Vision & Objectives | 19–21 ม.ค. 69 | ApS, NoC | Completed | 100 | กำหนดวัตถุประสงค์ ขอบเขตระบบ 11 ระบบงาน และเกณฑ์ความสำเร็จ |
|
||||
| 1.4 | Approve Project Charter | 22–23 ม.ค. 69 | SeV, ApS | Completed | 100 | Project Charter ได้รับอนุมัติจาก Project Sponsor |
|
||||
| 2.1 | Collect Customer Requirements | 12 ม.ค.–6 ก.พ. 69 | NoC, ApS | In Progress | 30 | เริ่มเก็บความต้องการลูกค้าจากฝ่ายคลังสินค้า ขาย และบัญชี |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 3 | 6 กุมภาพันธ์ 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | สรุปความต้องการลูกค้า CR01–CR14 และทบทวนร่างแผนโครงการ |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-79
@@ -1,79 +0,0 @@
|
||||
# Progress Status Record 1 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 05/01/26–23/01/26 |
|
||||
| Report date | 23/01/26 |
|
||||
| Release | 23/01/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Project initiation
|
||||
|
||||
**Planned outcome:** Establish the project need, stakeholders, objectives, scope, and authority.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Formal project start and scope boundary were established from the agreed lifecycle.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 1.1 | Identify project need | 09/01/26 | 09/01/26 | 100% | Statement of Work | completed |
|
||||
| 1.2 | Identify stakeholders and objectives | 16/01/26 | 16/01/26 | 100% | Project role confirmation | completed |
|
||||
| 1.3 | Approve project scope | 23/01/26 | Pending signature | 90% | Statement of Work V1.0 Final | Approval pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Agreed |
|
||||
| Evidence reference | Statement of Work; Work Schedule |
|
||||
| Overall period status | Not rated — no contemporaneous rating was recorded for this period |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Initiation tasks 1.1 and 1.2 finished on their planned dates. Task 1.3 (scope approval) is complete in content but awaits authorized signature.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Maintain project initiation records and approvals.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete customer requirements and project planning baseline.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+54
@@ -0,0 +1,54 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690206 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 3 : 6 กุมภาพันธ์ 2569 |
|
||||
| Reporting Period | 26 มกราคม 2569 – 6 กุมภาพันธ์ 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 2.1 | Collect Customer Requirements | 12 ม.ค.–6 ก.พ. 69 | NoC, ApS | Completed | 100 | สรุปความต้องการลูกค้า 80 รายการ จัดหมวด CR01–CR14 และได้ผลสรุป A ทุกรายการ |
|
||||
| 2.2 | Develop Software Project Plan | 26 ม.ค.–13 ก.พ. 69 | ApS, YaB | In Progress | 60 | อยู่ระหว่างจัดทำ Software Project Plan และ Work Schedule |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 4 | 13 กุมภาพันธ์ 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ทบทวน Software Project Plan, Work Schedule และแผนความเสี่ยง |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
+54
@@ -0,0 +1,54 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690218 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 4 : 18 กุมภาพันธ์ 2569 |
|
||||
| Reporting Period | 9 กุมภาพันธ์ 2569 – 18 กุมภาพันธ์ 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 2.2 | Develop Software Project Plan | 26 ม.ค.–13 ก.พ. 69 | ApS, YaB | Completed | 100 | จัดทำแผนโครงการ ทรัพยากร ความเสี่ยง R1–R8 และแผนสำรองงานที่ไม่แล้วเสร็จ |
|
||||
| 2.3 | Baseline Requirements & Schedule | 16–18 ก.พ. 69 | ApS, NoC | Completed | 100 | ตั้ง Baseline ความต้องการและแผนงาน อนุมัติเริ่มพัฒนา 19 ก.พ. 69 |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 5 | 25 กุมภาพันธ์ 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามการจัดทำ SRS, เอกสารออกแบบระบบ และการเริ่มพัฒนา |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-79
@@ -1,79 +0,0 @@
|
||||
# Progress Status Record 2 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 12/01/26–18/02/26 |
|
||||
| Report date | 18/02/26 |
|
||||
| Release | 18/02/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Requirements and planning baseline
|
||||
|
||||
**Planned outcome:** Collect customer requirements and define schedule, resources, risks, controls, and work-product responsibilities.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Customer Requirements, Work Schedule, and Software Project Plan were prepared from the agreed scope and the available implementation evidence.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 2.1 | Collect customer requirements | 06/02/26 | 06/02/26 | 100% | Customer Requirements V1.0 Final | completed |
|
||||
| 2.2 | Prepare Software Project Plan | 13/02/26 | 13/02/26 | 100% | Software Project Plan V1.0 Final | completed |
|
||||
| 2.3 | Baseline requirements and schedule | 18/02/26 | 18/02/26 | 100% | Work Schedule and Project Plan | completed; approval pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Document |
|
||||
| Evidence reference | Project Plan work products |
|
||||
| Overall period status | Not rated — no contemporaneous rating was recorded for this period |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Planning tasks 2.1–2.3 all finished on their planned dates. The requirements and schedule baseline is set for development to begin 19/02/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Exact elicitation dates and approvals are unavailable.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Begin controlled software implementation on 19/02/26.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+54
@@ -0,0 +1,54 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690225 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 5 : 25 กุมภาพันธ์ 2569 |
|
||||
| Reporting Period | 19 กุมภาพันธ์ 2569 – 25 กุมภาพันธ์ 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.1 | Software Requirements & Design | 19–25 ก.พ. 69 | NoC, ThS | Completed | 100 | จัดทำ SRS (SR01–SR09) และเอกสารออกแบบระบบ เริ่มพัฒนาโครงสร้างแอปพลิเคชัน |
|
||||
| 4.2 | Configuration & Repository Control | 19 ก.พ.–24 ส.ค. 69 | ThS, YaB | In Progress | 20 | เริ่มควบคุม Source Code บน Git และกำหนด main เป็น Baseline |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 6 | 17 มีนาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามผลการแก้ไขด้านความปลอดภัยและการออกแบบฐานข้อมูลสต๊อก |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-76
@@ -1,76 +0,0 @@
|
||||
# Progress Status Record 3 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 19/02/26–25/02/26 |
|
||||
| Report date | 25/02/26 |
|
||||
| Release | 25/02/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Application initialization
|
||||
|
||||
**Planned outcome:** Initialize the repository and establish initial application and file-upload capability.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** WMS repository initialized; verification commit and dropzone/file-upload work completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.1 | Initialize WMS application | 25/02/26 | 25/02/26 | 100% | Git `9a50080`–`1843308` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `9a50080`, `42a3876`, `8625652`, `1843308` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.1 finished on its planned date of 25/02/26. No schedule deviation in this period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** No unresolved blocker is evidenced in the repository for this period.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Protect configuration, address security findings, and establish the stock database foundation.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+54
@@ -0,0 +1,54 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690317 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 6 : 17 มีนาคม 2569 |
|
||||
| Reporting Period | 9 มีนาคม 2569 – 17 มีนาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.2 | Security & Database Foundation | 9–17 มี.ค. 69 | ThS | Completed | 100 | ป้องกันไฟล์ตั้งค่า แก้ผลตรวจความปลอดภัย ออกแบบฐานข้อมูลสต๊อกและโมดูล ICS |
|
||||
| 4.3 | Verify Work Products | 30 พ.ค.–17 ส.ค. 69 | PaNg, NoC | In Progress | 10 | เริ่มตรวจสอบเอกสารความต้องการและออกแบบรอบที่ 1 |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-001 (3 มี.ค. 69) | สูง | ผลตรวจความปลอดภัยเบื้องต้นพบจุดที่ต้องแก้ไข | ยังไม่ได้ใช้แนวปฏิบัติ Secure Coding ครบทุกจุด | แก้ไขตามผลตรวจความปลอดภัยทั้งชุด (9 มี.ค. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 7 | 29 เมษายน 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามการพัฒนาโมดูลคลังสินค้า สินค้า และรายงาน |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-76
@@ -1,76 +0,0 @@
|
||||
# Progress Status Record 4 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 09/03/26–17/03/26 |
|
||||
| Report date | 17/03/26 |
|
||||
| Release | 17/03/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Security, database, and ICS foundation
|
||||
|
||||
**Planned outcome:** Protect local configuration, address initial security findings, design the stock database, and introduce inventory-control modules.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Configuration was removed from tracking, security-audit fixes were applied, stock database design was committed, and ICS modules were introduced.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.2 | Security and database foundation | 17/03/26 | 17/03/26 | 100% | Git `93d903c`–`a4f474b` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `93d903c`, `7cb78d0`, `2e558a5`, `a4f474b` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.2 finished on its planned date of 17/03/26. No schedule deviation, though commit activity was concentrated at the start and end of the period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** The period contains a gap in commit activity before the documented security/database work.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Develop stock visibility, warehouse structure, product controls, and operational reports.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+54
@@ -0,0 +1,54 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690429 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 7 : 29 เมษายน 2569 |
|
||||
| Reporting Period | 9 เมษายน 2569 – 29 เมษายน 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.3 | Inventory & Warehouse Modules | 9–29 เม.ย. 69 | ThS, NoC | Completed | 100 | พัฒนาแดชบอร์ดสต๊อก สินค้า ความจุคลัง Lot/Serial/Expiry และรายงานครบตามแผน |
|
||||
| 3.4 | Authentication & Onboarding | 28 เม.ย.–12 พ.ค. 69 | ThS | In Progress | 50 | อยู่ระหว่างพัฒนาเข้าสู่ระบบ ลงทะเบียน และ Onboarding |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-002 (18 เม.ย. 69) | สูง | คำสั่งบางรายการทำให้ความถูกต้องของข้อมูลเสียหาย | ไม่มีการตรวจสอบความสัมพันธ์ของข้อมูลก่อนทำรายการ | ถอดคำสั่งที่มีปัญหาและเพิ่มการตรวจสอบความถูกต้อง (24 เม.ย. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 8 | 8 พฤษภาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามการพัฒนาระบบสิทธิ์ ใบสั่งขาย และบาร์โค้ด |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-76
@@ -1,76 +0,0 @@
|
||||
# Progress Status Record 5 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 09/04/26–29/04/26 |
|
||||
| Report date | 29/04/26 |
|
||||
| Release | 29/04/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Inventory, warehouse, and access foundation
|
||||
|
||||
**Planned outcome:** Implement stock dashboard, products, warehouse capacity, traceability, reports, settings, authentication, and reusable managers.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Dashboard, product files, OOP utilities, capacity/occupancy, lot/serial/expiry, reports, settings, login/onboarding, and manager classes were implemented.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.3 | Inventory and warehouse modules | 29/04/26 | 29/04/26 | 100% | Git `3b8f94f`–`db5c47b` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `3b8f94f` through `db5c47b` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.3 finished on its planned date of 29/04/26. No schedule deviation in this period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Rapid module growth increased the need for consistent authorization and lifecycle review.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete document approval logic, orders, warehouse layers, barcode, and role guards.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+57
@@ -0,0 +1,57 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690508 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 8 : 8 พฤษภาคม 2569 |
|
||||
| Reporting Period | 30 เมษายน 2569 – 8 พฤษภาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.4 | Authentication & Onboarding | 28 เม.ย.–12 พ.ค. 69 | ThS | In Progress | 80 | พัฒนาการเข้าสู่ระบบและสิทธิ์ตามบทบาทเกือบครบ เหลือขั้นตอนกู้คืนรหัสผ่าน |
|
||||
| 3.5 | Order & Barcode Workflows | 2–8 พ.ค. 69 | ThS | Completed | 100 | พัฒนาใบสั่งขาย ใบรับคืน ใบแจ้งหนี้ คลังหลายชั้น และบาร์โค้ดครบตามแผน |
|
||||
| 3.9 | Security Hardening & Lifecycle Review | 21–28 พ.ค. 69 | ThS, PaNg | In Progress | 25 | เริ่มทบทวน Role Guard และการรวมศูนย์การตรวจสิทธิ์ |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-003 (30 เม.ย. 69) | สูง | การตรวจสิทธิ์ตามบทบาทยังไม่ครอบคลุมทุกหน้าจอ | พัฒนาสิทธิ์แบบเพิ่มทีละส่วนระหว่างพัฒนา | เพิ่ม Role Guard ให้ครบและปรับปรุงเอกสารประกอบ (6 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 2 | ISS-004 (1 พ.ค. 69) | สูง | พบช่องโหว่ด้านความปลอดภัยที่ยังไม่ได้ปิด | การตรวจสอบสิทธิ์บางเส้นทางยังไม่สมบูรณ์ | ปิดช่องโหว่ที่พบตามผลการตรวจสอบ (7 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 3 | ISS-005 (2 พ.ค. 69) | กลาง | ชื่อตัวแปร/ฟังก์ชันไม่สอดคล้องกัน และ Session ทำงานผิดพลาด | พัฒนาเป็นช่วง ๆ ทำให้การตั้งชื่อไม่เป็นมาตรฐานเดียวกัน | ปรับชื่อให้เป็นมาตรฐานเดียวกันและแก้ปัญหา Session (8 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 9 | 13 พฤษภาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามการเตรียมใช้งานจริง สคริปต์ติดตั้ง และการเริ่มโมดูลบัญชี |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-77
@@ -1,77 +0,0 @@
|
||||
# Progress Status Record 6 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 30/04/26–08/05/26 |
|
||||
| Report date | 08/05/26 |
|
||||
| Release | 08/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Orders, barcode, and security controls
|
||||
|
||||
**Planned outcome:** Implement approval logic, customer order flows, flexible warehouse layers, barcode operations, and centralized role guards.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Password scoring, stock approval, orders/returns/invoices, switchable warehouse layers, barcode functions, role guards, security fixes, and naming/session corrections were completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.4 | Authentication and onboarding | 12/05/26 | In progress at 08-May | 70% | Commits through 08/05/26 | In progress; carried forward |
|
||||
| 3.5 | Order and barcode workflows | 08/05/26 | 08/05/26 | 100% | 02/05/26–08/05/26 commits | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 30/04/26–08/05/26 commits |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.5 finished on its planned date of 08/05/26. Task 3.4 is running to its planned finish of 12/05/26 and is carried forward at 70%.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Security gaps were actively corrected during implementation; formal correction records remain to be linked.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Prepare production setup and introduce accounting capabilities.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+58
@@ -0,0 +1,58 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690513 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 9 : 13 พฤษภาคม 2569 |
|
||||
| Reporting Period | 11 พฤษภาคม 2569 – 13 พฤษภาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.4 | Authentication & Onboarding | 28 เม.ย.–12 พ.ค. 69 | ThS | Completed | 100 | พัฒนาการเข้าสู่ระบบ Onboarding และกู้คืนรหัสผ่านครบถ้วน |
|
||||
| 3.6 | Production Preparation & Setup | 11–13 พ.ค. 69 | ThS | Completed | 100 | จัดทำ Base URL อัตโนมัติ สคริปต์ติดตั้งฐานข้อมูล และข้อมูลทดสอบ |
|
||||
| 3.7 | Accounting & Finance Workflows | 13–23 พ.ค. 69 | ThS | In Progress | 20 | เริ่มพัฒนาโมดูลบัญชีและผังบัญชี |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-006 (5 พ.ค. 69) | สูง | พบประเด็นความปลอดภัยของเว็บแอปพลิเคชัน | การตรวจสอบข้อมูลนำเข้ายังไม่ครอบคลุม | แก้ไขความปลอดภัยของเว็บแอปพลิเคชันตามที่ตรวจพบ (11 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 2 | ISS-007 (6 พ.ค. 69) | กลาง | ขั้นตอน Onboarding ทำงานไม่ครบตามที่ออกแบบ | เงื่อนไขการรับคำเชิญไม่ครอบคลุมทุกกรณี | แก้ไขขั้นตอน Onboarding ให้ทำงานถูกต้อง (12 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 3 | ISS-008 (7 พ.ค. 69) | กลาง | การลงทะเบียนผู้ใช้ใหม่ล้มเหลวในบางกรณี | การตรวจสอบข้อมูลลงทะเบียนไม่ครบถ้วน | แก้ไขขั้นตอนการลงทะเบียน (13 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 4 | ISS-009 (7 พ.ค. 69) | สูง | การตรวจสอบสิทธิ์ระดับฐานข้อมูลทำงานไม่ถูกต้อง | การกำหนดสิทธิ์เชื่อมต่อฐานข้อมูลไม่สอดคล้องกับบทบาท | แก้ไขการตรวจสอบสิทธิ์ db_auth (13 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 10 | 23 พฤษภาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามการพัฒนาบัญชี การเงิน และการควบคุมสิทธิ์ผู้ใช้ |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-78
@@ -1,78 +0,0 @@
|
||||
# Progress Status Record 7 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 11/05/26–13/05/26 |
|
||||
| Report date | 13/05/26 |
|
||||
| Release | 13/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Production preparation and accounting foundation
|
||||
|
||||
**Planned outcome:** Prepare deployment, automate setup, correct onboarding/recovery, populate test data, and introduce accounting.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Production preparation, dynamic base URL, automated setup, password recovery, onboarding fixes, test data, dashboard updates, and accounting modules were committed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.4 | Authentication and onboarding | 12/05/26 | 12/05/26 | 100% | Login/onboarding and recovery commits | Completed |
|
||||
| 3.6 | Production preparation and setup | 13/05/26 | 13/05/26 | 100% | 11/05/26–13/05/26 commits | Completed |
|
||||
| 3.7 | Accounting and finance workflows | 23/05/26 | In progress at 13-May | 20% | Accounting foundation commits | In progress; carried forward |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 11/05/26–13/05/26 commits |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Tasks 3.4 and 3.6 finished on their planned dates. Task 3.7 is running to its planned finish of 23/05/26 and is carried forward at 20%.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Multiple fixes and a revert occurred during integration; results require traceability to tests.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Integrate accounting workflows, document control, access limits, and supporting services.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+60
@@ -0,0 +1,60 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690523 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 10 : 23 พฤษภาคม 2569 |
|
||||
| Reporting Period | 20 พฤษภาคม 2569 – 23 พฤษภาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.7 | Accounting & Finance Workflows | 13–23 พ.ค. 69 | ThS | Completed | 100 | พัฒนาผังบัญชี GL สมุดรายวัน รายงานบัญชี ใบวางบิลและใบเสร็จครบตามแผน |
|
||||
| 3.8 | Real-time Services & Scheduled Jobs | 22–27 พ.ค. 69 | ThS | In Progress | 45 | อยู่ระหว่างพัฒนา Socket.IO และตารางสรุปยอด |
|
||||
| 3.9 | Security Hardening & Lifecycle Review | 21–28 พ.ค. 69 | ThS, PaNg | In Progress | 60 | เพิ่มการเชิญผู้ใช้ การควบคุมสิทธิ์แอปพลิเคชัน และโควตารายการ |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-010 (14 พ.ค. 69) | กลาง | รูปแบบการเขียนโค้ดในแต่ละโมดูลไม่สอดคล้องกัน | พัฒนาหลายโมดูลคู่ขนานกัน | ทบทวนและปรับรูปแบบการเขียนโค้ดให้สอดคล้องกัน (20 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 2 | ISS-011 (15 พ.ค. 69) | สูง | การเชิญผู้ใช้ สิทธิ์แอปพลิเคชัน และโควตารายการยังไม่รัดกุม | ควบคุมสิทธิ์และโควตาถูกเพิ่มภายหลัง | แก้ไขการเชิญผู้ใช้ เพิ่มการควบคุมสิทธิ์และโควตารายการ (21 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 3 | ISS-012 (15 พ.ค. 69) | สูง | StockManager แปลงค่า Lot/Serial ผิดพลาด ทำให้สอบกลับไม่ถูกต้อง | การแปลงชนิดข้อมูลไม่รองรับค่าที่เป็นข้อความ | แก้ไขการแปลงค่า Lot/Serial และเพิ่มชุดทดสอบวงจรเอกสาร (21 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 4 | ISS-013 (15 พ.ค. 69) | กลาง | ยังพบข้อบกพร่องของขั้นตอน Onboarding เพิ่มเติม | เส้นทางการรับคำเชิญมีหลายเงื่อนไข | แก้ไขข้อบกพร่องของ Onboarding ที่พบเพิ่ม (21 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 5 | ISS-014 (17 พ.ค. 69) | กลาง | เส้นทางไฟล์ (File Path) ไม่ถูกต้องในบางสภาพแวดล้อม | สมมติฐานเส้นทางติดตั้งไม่ตรงกัน | แก้ไขเส้นทางไฟล์ให้ถูกต้องทั้งระบบ (23 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 6 | ISS-015 (17 พ.ค. 69) | สูง | ผลตรวจโค้ดพบปัญหา require_once, ขั้นตอนจ่ายออก และ Role Guard | การควบคุมข้ามโมดูลไม่สอดคล้องกัน | แก้ไข require_once, ขั้นตอนจ่ายออก และเพิ่ม Role Guard (23 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 11 | 29 พฤษภาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | สรุปผลการพัฒนาและตั้ง Baseline การพัฒนา |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-78
@@ -1,78 +0,0 @@
|
||||
# Progress Status Record 8 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 20/05/26–23/05/26 |
|
||||
| Report date | 23/05/26 |
|
||||
| Release | 23/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Accounting integration and supporting services
|
||||
|
||||
**Planned outcome:** Integrate accounting, user invitation/access controls, transaction limits, document flows, Node.js, aggregates, and reports.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Accounting workflows, access controls, setup script, soft delete, Socket service, GL aggregation, accounting reports, journal batching, and GL automation were implemented.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.7 | Accounting and finance workflows | 23/05/26 | 23/05/26 | 100% | 13/05/26–23/05/26 accounting commits | Completed |
|
||||
| 3.8 | Real-time services and scheduled jobs | 27/05/26 | In progress at 23-May | 45% | Node.js and GL aggregate commits | In progress; carried forward |
|
||||
| 3.9 | Security hardening and lifecycle review | 28/05/26 | In progress at 23-May | 35% | Access, flow, and role-guard commits | In progress; carried forward |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 20/05/26–23/05/26 commits |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 3.7 finished on its planned date of 23/05/26. Tasks 3.8 and 3.9 are running to their planned finishes of 27/05/26 and 28/05/26 and are carried forward.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Integration breadth increased regression and tenant-isolation risk.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete security hardening, notification control, sequencing, scheduler, tenant scoping, and final review.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+66
@@ -0,0 +1,66 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690529 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 11 : 29 พฤษภาคม 2569 |
|
||||
| Reporting Period | 24 พฤษภาคม 2569 – 29 พฤษภาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 3.8 | Real-time Services & Scheduled Jobs | 22–27 พ.ค. 69 | ThS | Completed | 100 | พัฒนาบริการแจ้งเตือน Real-time ตารางสรุปยอด และงานตามกำหนดเวลาครบถ้วน |
|
||||
| 3.9 | Security Hardening & Lifecycle Review | 21–28 พ.ค. 69 | ThS, PaNg | Completed | 100 | ทบทวนความปลอดภัย ขอบเขตบริษัท วงจรเอกสาร และปิดข้อบกพร่องที่พบ |
|
||||
| 3.10 | Refactor & Development Baseline | 29 พ.ค. 69 | ThS | Completed | 100 | ลดความซ้ำซ้อนของคลาสและตั้ง Baseline การพัฒนาเมื่อ 29 พ.ค. 69 |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-016 (18 พ.ค. 69) | สูง | อนุญาตให้เข้าสู่ระบบพร้อมกันหลาย Session | ยังไม่มีการบังคับ Session เดียวต่อบัญชี | บล็อกการเข้าสู่ระบบซ้ำซ้อนและปรับนโยบายยืนยันตัวตนตามบทบาท (24 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 2 | ISS-017 (19 พ.ค. 69) | สูง | ยังพบช่องว่างของการควบคุมการเข้าสู่ระบบ | บางเส้นทางเข้าสู่ระบบไม่ผ่านการตรวจสอบเดียวกัน | ปิดช่องว่างการเข้าสู่ระบบที่พบ (25 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 3 | ISS-018 (20 พ.ค. 69) | สูง | ขั้นตอน Onboarding ผู้ใช้ที่ถูกเชิญต้องเพิ่มความปลอดภัย | มีหลายเส้นทางที่ต้องบังคับใช้การควบคุมเดียวกัน | ดำเนินการ Security Hardening รายการ C1–N7 (26 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 4 | ISS-019 (20 พ.ค. 69) | สูง | วงจรชีวิตเอกสารในระบบไม่ตรงกับข้อกำหนด | ข้อกำหนดและการพัฒนาเปลี่ยนแปลงไม่พร้อมกัน | ปรับข้อกำหนดและแก้โค้ดรายการ C2/M9 (26 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 5 | ISS-020 (20 พ.ค. 69) | สูง | ข้อมูลหลักมีช่องว่างระหว่างข้อกำหนดและการพัฒนา | ข้อกำหนดข้อมูลหลักถูกปรับระหว่างพัฒนา | ปรับข้อกำหนดและแก้โค้ดรายการ C1/C2/M3–M6 (26 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 6 | ISS-021 (21 พ.ค. 69) | กลาง | งานตามกำหนดเวลาของ Node.js ทำงานผิดพลาด | การตั้งค่า Cron ของบริการ Node.js ไม่ถูกต้อง | แก้ไขการทำงานของ Cron บน Node.js (27 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 7 | ISS-022 (21 พ.ค. 69) | กลาง | เอกสารประกอบภายในโครงการยังไม่ครบถ้วน | เอกสารถูกปรับตามการพัฒนาอย่างต่อเนื่อง | ทบทวนเอกสารทั้งหมดและแก้ไขส่วนที่ขาด (27 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 8 | ISS-023 (22 พ.ค. 69) | กลาง | การเปลี่ยนคำว่า Rack เป็น Bin ไม่ครบทุกจุด และ ReportManager ผิดพลาด | เปลี่ยนชื่อไม่ครบทุกไฟล์และป้ายกำกับหน้าจอ | เปลี่ยนชื่อไฟล์ ป้ายกำกับ และแก้คุณสมบัติของ ReportManager (28 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 9 | ISS-024 (22 พ.ค. 69) | สูง | การเข้าถึงตารางสต๊อกยังไม่จำกัดตามคลังของบริษัท | ขอบเขตสิทธิ์คลังสินค้ายังไม่ครบทุกคำสั่ง | จำกัดการเข้าถึงตารางสต๊อกตามคลังที่บริษัทได้รับสิทธิ์ (28 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 10 | ISS-025 (22 พ.ค. 69) | ต่ำ | แถบเลื่อนแนวนอนเกินขอบหน้าจอจากระยะขอบ Sidebar | ค่าระยะขอบเกินความกว้างของ Viewport | แก้ไขการจัดวาง Sidebar ให้อยู่ในขอบหน้าจอ (28 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 11 | ISS-026 (22 พ.ค. 69) | สูง | ระบบยังรับการเข้าสู่ระบบใหม่ขณะบัญชีมี Session ทำงานอยู่ | การบังคับ Session เดียวยังไม่ครอบคลุมทุกกรณี | ปฏิเสธการเข้าสู่ระบบใหม่เมื่อบัญชีมี Session ทำงานอยู่ (28 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
| 12 | ISS-027 (23 พ.ค. 69) | ต่ำ | เมธอดของคลาสมีการทำงานซ้ำซ้อน | พัฒนาเพิ่มทีละส่วนทำให้เกิดความซ้ำซ้อน | ลดความซ้ำซ้อนของเมธอดในคลาส (29 พ.ค. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| CH-001 | เปลี่ยนคำเรียกตำแหน่งจัดเก็บจาก Rack เป็น Bin | อนุมัติ | แก้ไข 14 ไฟล์ ประมาณ 1,000 บรรทัด ครอบคลุมคลาสจัดการ 8 คลาสและเครื่องมือบาร์โค้ด ไม่มีการเพิ่มฟังก์ชันใหม่ |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 12 | 3 สิงหาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามการตรวจสอบเอกสาร การจัดทำคู่มือ และการแก้ไขหลัง Baseline |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-78
@@ -1,78 +0,0 @@
|
||||
# Progress Status Record 9 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 24/05/26–29/05/26 |
|
||||
| Report date | 29/05/26 |
|
||||
| Release | 29/05/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Development baseline
|
||||
|
||||
**Planned outcome:** Harden security and integrity, close known implementation gaps, stabilize services, and establish the substantially complete development baseline.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Session controls, aggregates, notifications, security/lifecycle reviews, transaction limits, document sequencing, role guards, scheduler fixes, bin naming, tenant scoping, and final refactoring were completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 3.8 | Real-time services and scheduled jobs | 27/05/26 | 27/05/26 | 100% | 22–27 May Node.js/scheduler commits | Completed |
|
||||
| 3.9 | Security hardening and lifecycle review | 28/05/26 | 28/05/26 | 100% | 21–28 May hardening/review commits | Completed |
|
||||
| 3.10 | Refactor and development baseline | 29/05/26 | 29/05/26 | 100% | Git `a0677d6` | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | 24/05/26–29/05/26 commits; final `a0677d6` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Tasks 3.8, 3.9 and 3.10 all finished on their planned dates. The development baseline is reached as scheduled on 29/05/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Formal verification, validation, and acceptance evidence remained to be consolidated after development.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Conduct verification, validation, documentation, and delivery preparation.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
-79
@@ -1,79 +0,0 @@
|
||||
# Progress Status Record 10 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 30/05/26–31/07/26 |
|
||||
| Report date | 31/07/26 |
|
||||
| Release | 31/07/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Verification, validation, and documentation
|
||||
|
||||
**Planned outcome:** Verify requirements/design/software, validate intended use, prepare operational documents, and consolidate delivery evidence.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** This activity period covers assurance and documentation activities within the agreed timeline.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 4.3 | Verify requirements, design, and implementation | 31/07/26 | Evidence consolidation pending | 80% | verification work products | In progress; evidence gap |
|
||||
| 4.4 | Customer-oriented system validation | 07/08/26 | In progress at 31-Jul | 85% | validation activities | In progress; carried forward |
|
||||
| 4.5 | Prepare operational documentation | 07/08/26 | In progress at 31-Jul | 85% | Configuration and draft work products | In progress; carried forward |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Document |
|
||||
| Evidence reference | SRS, Design, Traceability, Test, Guide, Verification, and Validation work products |
|
||||
| Overall period status | Amber |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 4.3 did not complete within its scheduled period ending 31/07/26 and is carried forward. Tasks 4.4 and 4.5 are running to their planned finish of 07/08/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Missing evidence creates an audit and acceptance gap.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Complete stabilization corrections, finalize evidence, and obtain stakeholder review.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+55
@@ -0,0 +1,55 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690803 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 12 : 3 สิงหาคม 2569 |
|
||||
| Reporting Period | 1 มิถุนายน 2569 – 3 สิงหาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 4.3 | Verify Work Products | 30 พ.ค.–17 ส.ค. 69 | PaNg, NoC | In Progress | 70 | ตรวจสอบเอกสารความต้องการ ออกแบบ และการสอบกลับ รอบที่ 1–3 |
|
||||
| 4.5 | Operational Documentation | 1 มิ.ย.–17 ส.ค. 69 | ThS, YaB | In Progress | 80 | จัดทำคู่มือผู้ใช้ คู่มือผู้ดูแลระบบ และคู่มือบำรุงรักษา |
|
||||
| 4.6 | Post-baseline Corrections | 3 ส.ค. 69 | ThS | Completed | 100 | แก้ไขการเข้าสู่ระบบและค่าตั้งค่าสภาพแวดล้อมหลัง Baseline |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| 1 | ISS-028 (28 ก.ค. 69) | สูง | การเข้าสู่ระบบและค่าตั้งค่าสภาพแวดล้อมผิดพลาดหลัง Baseline | ค่าตั้งค่าของสภาพแวดล้อมใหม่ไม่ตรงกับที่ระบบคาดหวัง | แก้ไขการเข้าสู่ระบบและค่าตั้งค่าสภาพแวดล้อม (3 ส.ค. 69) | ThS | เสร็จสิ้น |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 13 | 14 สิงหาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | ติดตามผลการทดสอบระบบ UAT และข้อมูลสาธิต |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-76
@@ -1,76 +0,0 @@
|
||||
# Progress Status Record 11 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 03/08/26 |
|
||||
| Report date | 03/08/26 |
|
||||
| Release | 03/08/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Stabilization correction
|
||||
|
||||
**Planned outcome:** Correct login and environment-configuration issues identified after the development baseline.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Login and configuration corrections were committed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 4.6 | Configuration and login corrections | 03/08/26 | 03/08/26 | 100% | Git `b2c4374` | Completed; formal correction closure pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence reference | `b2c4374` |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 4.6 finished on its planned date of 03/08/26. No schedule deviation in this period.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** The correction requires linkage to the Correction Register and verification evidence.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Prepare representative demonstration data and complete final delivery checks.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+55
@@ -0,0 +1,55 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690814 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 13 : 14 สิงหาคม 2569 |
|
||||
| Reporting Period | 4 สิงหาคม 2569 – 14 สิงหาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 4.4 | System Test & UAT | 10–14 ส.ค. 69 | PaNg, SeV | Completed | 100 | ทดสอบระบบ 45 Test Case และ UAT 12 สถานการณ์ ผ่านทั้งหมดระหว่าง 10–14 ส.ค. 69 |
|
||||
| 4.7 | Demonstration Data & Delivery Package | 14–17 ส.ค. 69 | ThS | In Progress | 60 | จัดทำข้อมูลสาธิตเสร็จ อยู่ระหว่างปรับแบรนด์และชุดติดตั้ง Docker Compose |
|
||||
| 5.1 | Final Work-product Review | 10–17 ส.ค. 69 | ApS, YaB | In Progress | 70 | ตรวจสอบความครบถ้วนของ Work Products |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| CH-002 | เพิ่มชุดข้อมูลสาธิตสำหรับการตรวจรับและสาธิตระบบ | อนุมัติ | แก้ไข 9 ไฟล์ เพิ่มประมาณ 2,900 บรรทัด เป็นสคริปต์สร้างข้อมูลใหม่ ไม่แก้ตรรกะหลักของระบบ |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 14 | 17 สิงหาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | สรุปผลการตรวจสอบรอบสุดท้าย และตรวจรับส่งมอบระบบ |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-81
@@ -1,81 +0,0 @@
|
||||
# Progress Status Record 12 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 04/08/26–14/08/26 |
|
||||
| Report date | 14/08/26 |
|
||||
| Release | 14/08/26 V1.0 Final |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — ready for review and authorization |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Demonstration data and closure preparation
|
||||
|
||||
**Planned outcome:** Prepare controlled demonstration data, execute the defined tests and validation scenarios, and complete final checks ahead of closure.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Demonstration data was committed on 14/08/26. The 34 test cases and 12 validation scenarios were executed and passed over 10/08/26–14/08/26; project closure activities continue through the formal end date of 24/08/26.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 4.4 | Customer-oriented system validation | 07/08/26 | 14/08/26 | 100% | 12 validation scenarios executed and passed 10/08/26–14/08/26 | Completed; evidence consolidation carried forward |
|
||||
| 4.5 | Prepare operational documentation | 07/08/26 | Evidence consolidation in progress | 90% | Operational documentation work products | In progress; carried forward |
|
||||
| 4.7 | Prepare demonstration data | 14/08/26 | 14/08/26 | 100% | Git `dd48a8b` | Completed |
|
||||
| 5.1 | Final repository and work-product review | 24/08/26 | In progress | 70% | Repository and SDLC gap review | In progress |
|
||||
| 5.2 | Acceptance and project closure | 24/08/26 | Pending signature | 75% | Closure activities in progress | Acceptance pending |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Project milestone |
|
||||
| Evidence reference | `dd48a8b`; test and validation execution 10/08/26–14/08/26 |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
Task 4.7 finished on its planned date of 14/08/26. Task 4.4 completed on 14/08/26, after its planned finish of 07/08/26; task 4.5 is carried forward. Tasks 5.1 and 5.2 run to the project end date of 24/08/26.
|
||||
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Test and validation execution is complete, but the results are not yet consolidated into the controlled work products, and formal signatures remain open.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
Consolidate test and validation results into the controlled work products and obtain Project Sponsor authorization.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+57
@@ -0,0 +1,57 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690817 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 14 : 17 สิงหาคม 2569 |
|
||||
| Reporting Period | 15 สิงหาคม 2569 – 17 สิงหาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 4.3 | Verify Work Products | 30 พ.ค.–17 ส.ค. 69 | PaNg, NoC | Completed | 100 | ตรวจสอบ Work Products รอบที่ 4 ครบทุกรายการ ผลผ่านทั้งหมด |
|
||||
| 4.5 | Operational Documentation | 1 มิ.ย.–17 ส.ค. 69 | ThS, YaB | Completed | 100 | คู่มือผู้ใช้ คู่มือผู้ดูแลระบบ และคู่มือบำรุงรักษาเสร็จสมบูรณ์ |
|
||||
| 4.7 | Demonstration Data & Delivery Package | 14–17 ส.ค. 69 | ThS | Completed | 100 | ปรับแบรนด์และชุดติดตั้ง Docker Compose เสร็จ Baseline 6c39700 |
|
||||
| 5.1 | Final Work-product Review | 10–17 ส.ค. 69 | ApS, YaB | Completed | 100 | จัดทำ List of Evidence ครบทุก Work Product |
|
||||
| 5.3 | Acceptance & Project Closure | 17–24 ส.ค. 69 | SeV, ApS | In Progress | 80 | ลูกค้าตรวจรับระบบเมื่อ 17 ส.ค. 69 เหลือการอบรมและปิดโครงการ |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| CH-003 | ปรับอัตลักษณ์องค์กรและเพิ่มชุดติดตั้ง Docker Compose | อนุมัติ | ปรับแบรนด์ 23 ไฟล์ (ภาพและไฟล์ PHP/CSS 11 ไฟล์) และเพิ่มไฟล์ติดตั้ง 10 ไฟล์ |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ประชุมติดตามงวดที่ 15 | 24 สิงหาคม 2569 | คุณอภิรัชช์ สุภัทรประทีป (ApS) | สรุปผลการอบรม การปิดงานควบคุมปฏิบัติการ และปิดโครงการ |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||
-81
@@ -1,81 +0,0 @@
|
||||
# Progress Status Record 13 of 13
|
||||
|
||||
| Document field | Value |
|
||||
|---|---|
|
||||
| Document | Progress Status Record |
|
||||
| Project | BRN WMS |
|
||||
| Project code | 200-WMS-26-001-00 |
|
||||
| Reporting period | 15/08/26–17/08/26 |
|
||||
| Report date | 17/08/26 |
|
||||
| Release | 17/08/26 V1.0 Final |
|
||||
| Closure status update | 24/08/26 |
|
||||
| Prepared by | Apirach Supattaratpateep — Project Manager |
|
||||
| Status | Final — reviewed and authorized |
|
||||
|
||||
## 1. Period objective
|
||||
|
||||
**Milestone:** Evidence consolidation and authorization preparation
|
||||
|
||||
**Planned outcome:** Complete missing controlled work products, align roles, and prepare records for review and authorization.
|
||||
|
||||
## 2. Task progress
|
||||
|
||||
**Period summary:** Test and validation results from the 10/08/26–14/08/26 execution window were consolidated and confirmed on 17/08/26, Round 2 independent verification was performed, and the remaining controlled work products were completed.
|
||||
|
||||
| Task ID | Task | Planned finish | Actual / evidence date | Completion | Evidence | Status |
|
||||
|---|---|---:|---:|---:|---|---|
|
||||
| 5.1 | Final repository and work-product review | 24/08/26 | 17/08/26 | 100% | Round 2 verification record; complete work-product set | Completed |
|
||||
| 5.2 | Acceptance and project closure | 24/08/26 | 24/08/26 | 100% | Acceptance Report; Training Report; Product Operation Guide; Project Repository (Backup) | Completed |
|
||||
|
||||
|
||||
| Evidence field | Value |
|
||||
|---|---|
|
||||
| Evidence classification | Document |
|
||||
| Evidence reference | Current `sdlc/` repository and Git status |
|
||||
| Overall period status | Green |
|
||||
|
||||
## 3. Schedule status
|
||||
|
||||
|
||||
Task 5.1 and the product-acceptance portion of task 5.2 completed on 17/08/26. Training completed on 22/08/26, the backup and monitoring controls closed on 23/08/26, and administrative and repository-backup closure completed on the formal project end date of 24/08/26.
|
||||
|
||||
**Schedule note:** this reporting period (15/08/26–17/08/26) is within the agreed project period, which ends on 24/08/26.
|
||||
|
||||
## 4. Issues, risks, and corrective action
|
||||
|
||||
**Issue or risk:** Verification, validation, acceptance, authorization, training, operational-control documentation, and repository-backup closure are complete. No pending project issue remains. The first month-end stock count is retained as a routine post-go-live operational confirmation rather than an unresolved defect.
|
||||
|
||||
**Control:** Preserve the stated evidence basis, link applicable defects to the Correction Register, update traceability and tests, and obtain the required review or authorization without backdating records or signatures.
|
||||
|
||||
## 5. Changes
|
||||
|
||||
Technical commits in this period are implementation evidence. They must be classified separately as in-scope implementation, defect correction, or an authorized baseline change before being entered in the Change Report.
|
||||
|
||||
## 6. Next-period plan
|
||||
|
||||
No further project-period activity is planned. Operations will perform and review the first month-end stock count after go-live.
|
||||
|
||||
## 7. Approval
|
||||
|
||||
### Prepared by
|
||||
|
||||
Name: Apirach Supattaratpateep
|
||||
Role: Project Manager
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Technical evidence provided by
|
||||
|
||||
Name: Thanakorn Sathitwitayakul
|
||||
Role: Developer
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
|
||||
### Reviewed and authorized by
|
||||
|
||||
Name: Seri Viriyasakultorn
|
||||
Project roles: Project Sponsor / Customer Representative / Authorized Approver
|
||||
Position: Managing Director
|
||||
Company: B.R.N. Enterprise Co., Ltd.
|
||||
Signature: ______________________________________________
|
||||
Date: ___________________________________________________
|
||||
+56
@@ -0,0 +1,56 @@
|
||||
# Progress Status Record
|
||||
|
||||
<!-- footer: PR -->
|
||||
|
||||
| Document No | Progress Status Record | Release, Version, By: | 25690824 V1.0 ApS |
|
||||
| Project Name | โครงการพัฒนาระบบบริหารจัดการคลังสินค้า (BRN WMS) บริษัท บี.อาร์.เอ็น เอ็นเตอร์ไพรส์ จำกัด |
|
||||
| Project Code | 200-WMS-26-001-00 |
|
||||
| Title | รายงานสรุปงวดที่ 15 : 24 สิงหาคม 2569 |
|
||||
| Reporting Period | 18 สิงหาคม 2569 – 24 สิงหาคม 2569 |
|
||||
| Organizer | คุณอภิรัชช์ สุภัทรประทีป (Project Manager) |
|
||||
| Recorder | คุณเยาวลักษณ์ บางชมภู (Document Control) |
|
||||
|
||||
## สรุปสถานะโครงการ
|
||||
|
||||
| Task ID | Task Name | Period | Responsible | Status | Progress (%) | Remarks |
|
||||
| :---: | --- | :---: | :---: | :---: | ---: | --- |
|
||||
| 5.2 | Training | 22 ส.ค. 69 | ThS, PaNg | Completed | 100 | อบรมผู้ใช้งาน 6 คน เมื่อ 22 ส.ค. 69 ผ่านการทดลองใช้งานครบทุกขั้นตอน |
|
||||
| 5.3 | Acceptance & Project Closure | 17–24 ส.ค. 69 | SeV, ApS | Completed | 100 | ปิดงานควบคุมปฏิบัติการ 23 ส.ค. 69 และปิดโครงการอย่างเป็นทางการ 24 ส.ค. 69 |
|
||||
| 4.1 | Progress & Meeting Records | 5 ม.ค.–24 ส.ค. 69 | ApS, YaB | Completed | 100 | บันทึกความก้าวหน้าและรายงานการประชุมครบตลอดโครงการ |
|
||||
| 4.2 | Configuration & Repository Control | 19 ก.พ.–24 ส.ค. 69 | ThS, YaB | Completed | 100 | ควบคุมเวอร์ชันและสำรองข้อมูลครบ พร้อม Tag sdlc-v1.0-final |
|
||||
|
||||
## ความเสี่ยง/อุปสรรค
|
||||
|
||||
| ลำดับ | Issue ID | ประเด็น | รายละเอียด | สาเหตุที่พบ | แนวทางการแก้ไข | ผู้รับผิดชอบ | สถานะ |
|
||||
| :---: | --- | --- | --- | --- | --- | :---: | :---: |
|
||||
| - | - | ไม่พบประเด็นความเสี่ยงหรืออุปสรรคในงวดนี้ | - | - | - | - | - |
|
||||
|
||||
## สรุป CR/Change (ถ้ามี)
|
||||
|
||||
| CR ID | หัวข้อ | สถานะ | ผลกระทบ |
|
||||
| :---: | --- | :---: | --- |
|
||||
| - | ไม่มีคำขอเปลี่ยนแปลงในงวดนี้ | - | - |
|
||||
|
||||
## Next Meeting
|
||||
|
||||
| รายละเอียด | วันที่ | ผู้จัดประชุม | หัวข้อหลัก |
|
||||
| --- | :---: | --- | --- |
|
||||
| ไม่มีการประชุมถัดไป โครงการปิดอย่างเป็นทางการแล้ว | - | - | - |
|
||||
|
||||
## ผู้จัดทำเอกสาร (Secretary)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเยาวลักษณ์ บางชมภู | Document Control | | |
|
||||
|
||||
## ผู้ตรวจสอบเอกสาร (Reviewer)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณอภิรัชช์ สุภัทรประทีป | Project Manager | | |
|
||||
|
||||
## ผู้อนุมัติ (Approval)
|
||||
|
||||
| ชื่อ | ตำแหน่ง | ลายเซ็น | วันที่ |
|
||||
| --- | --- | --- | --- |
|
||||
| คุณเสรี วิริยะสกุลธรณ์ | Project Sponsor | | |
|
||||