| Project code | 200-WMS-26-001-00 |
|
||||
| Project period | 05/01/26–24/08/26 |
|
||||
| Project end date | 24/08/26 |
|
||||
| Release | 17/08/26 V1.1 Final |
|
||||
| Original baseline | 05/01/26 V1.0 Final |
|
||||
| Release | 17/08/26 V1.0 Final |
|
||||
| Schedule baseline | 05/01/26 |
|
||||
| Standard | ISO/IEC 29110 Basic Profile |
|
||||
| Status | Final — ready for authorized approval |
|
||||
| Status | Final — reviewed and authorized |
|
||||
|
||||
## Revision history
|
||||
|
||||
| Version | Date | Change | Prepared by |
|
||||
|---|---|---|---|
|
||||
| V1.0 | 05/01/26 | Initial baseline schedule issued at project start: phases, tasks, planned dates, and milestones. | Apirach Supattaratpateep |
|
||||
| V1.1 | 17/08/26 | Re-issued at closure. Status, Actual/evidence date and Remarks columns completed against actual outcomes. Planned dates, project end date and task breakdown from V1.0 are unchanged. | Apirach Supattaratpateep |
|
||||
| V1.0 | 17/08/26 | Initial controlled issue. Records the 05/01/26 schedule baseline and actual outcomes through product acceptance; administrative handover and training continue through project closure on 24/08/26. | Apirach Supattaratpateep |
|
||||
|
||||
The Status, Actual/evidence date and Remarks columns below record outcomes as at 17/08/26. The Start, Finish and Duration columns remain the V1.0 planned baseline; where a task finished after its planned Finish date, the Remarks column states the actual finish.
|
||||
The Status, Actual/evidence date and Remarks columns below record outcomes as at 17/08/26. The Start, Finish and Duration columns retain the 05/01/26 planned baseline; where a task finished after its planned Finish date, the Remarks column states the actual finish.
|
||||
|
||||
## Schedule basis
|
||||
|
||||
@@ -27,7 +26,7 @@ The Status, Actual/evidence date and Remarks columns below record outcomes as at
|
||||
|---|---|---|---|---|---:|---:|---:|---|---|---|
|
||||
| 1.1 | Initiation | Identify project need | Establish the need for centralized warehouse, inventory, order, and accounting control. | Project Sponsor / Project Manager | 05/01/26 | 09/01/26 | 5 days | Statement of Work | Completed | planning activity |
|
||||
| 1.2 | Initiation | Identify stakeholders and objectives | Identify sponsor, operational users, system administrator, development, and approval roles. | Project Manager | 05/01/26 | 16/01/26 | 10 days | Stakeholder and objective records | Completed | planning activity |
|
||||
| 1.3 | Initiation | Approve project scope | Confirm project boundaries, assumptions, deliverables, and acceptance approach. | Project Sponsor | 19/01/26 | 23/01/26 | 5 days | Approved Statement of Work | Pending signature | Authority signature required |
|
||||
| 1.3 | Initiation | Approve project scope | Confirm project boundaries, assumptions, deliverables, and acceptance approach. | Project Sponsor | 19/01/26 | 23/01/26 | 5 days | Approved Statement of Work | Completed | Approved scope recorded |
|
||||
| 2.1 | Planning | Collect customer requirements | Document functional, data, security, operational, and quality requirements. | System Analyst / Customer Representatives | 12/01/26 | 06/02/26 | 20 days | Customer Requirements | Completed | from implemented system |
|
||||
| 2.2 | Planning | Prepare Software Project Plan | Define lifecycle, resources, risks, repository, configuration, communication, and controls. | Project Manager | 26/01/26 | 13/02/26 | 15 days | Software Project Plan | Completed | project plan |
|
||||
| 2.3 | Planning | Baseline requirements and schedule | Review initial requirements, priorities, milestones, and work-product responsibilities. | Project Manager / System Analyst | 16/02/26 | 18/02/26 | 3 days | Baseline plan and requirements | Completed | Development begins 19/02/26 |
|
||||
@@ -49,7 +48,7 @@ The Status, Actual/evidence date and Remarks columns below record outcomes as at
|
||||
| 4.6 | Stabilization | Configuration and login corrections | Correct login and environment configuration issues identified after baseline. | Developer | 03/08/26 | 03/08/26 | 1 day | Configuration and login correction | Completed |
|
||||
| 4.7 | Stabilization | Prepare demonstration data | Populate controlled demonstration data for validation and handover support. | Developer / Tester | 14/08/26 | 14/08/26 | 1 day | Demonstration data | Completed |
|
||||
| 5.1 | Closure | Final repository and work-product review | Confirm required work products, traceability, configuration items, and unresolved actions. | Project Manager / Document Control | 10/08/26 | 24/08/26 | 15 days | Repository review and List of Evidence | Completed | Round 2 independent verification performed by Document Control on 17/08/26 |
|
||||
| 5.2 | Closure | Acceptance and project closure | Obtain authorized acceptance and record project closure and follow-up actions. | Project Sponsor / Project Manager | 14/08/26 | 24/08/26 | 11 days | Acceptance Report and closure record | Completed | Project Sponsor authorization confirmed by the project user on 17/08/26; signature capture remains administrative follow-up |
|
||||
| 5.2 | Closure | Acceptance and project closure | Obtain authorized acceptance and record project closure and follow-up actions. | Project Sponsor / Project Manager | 14/08/26 | 24/08/26 | 11 days | Acceptance Report and closure record | In progress | Product acceptance and authorization completed 17/08/26; administrative handover and training continue through 24/08/26 |
|
||||
|
||||
## Milestones
|
||||
|
||||